Unico Silver (USL) Q1 2027 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2027 TU earnings summary
28 Oct, 2026Executive summary
Quarter focused on de-risking the Joaquin development: initial La Mata estancia consideration secured surface rights for the resource areas and preferred infrastructure footprint.
The integrated Joaquin–Cerro Leon maiden PFS was rescheduled from September 2026 to January 2027 to incorporate an updated resource and further metallurgical and process testwork.
An institutional placement of ~A$60m was completed, supporting 20,000m of planned resource-growth drilling and funding the PFS and DFS work through end-2027.
Financial highlights
Quarter-end cash and cash equivalents were A$100.265m, compared with A$55.068m at the prior quarter end.
Cash flows included A$60.0m from equity issues, A$0.510m from option exercises, A$3.099m of equity-issue costs and A$0.649m net operating outflow.
Exploration and evaluation payments were A$6.337m; property, plant and equipment payments were A$5.228m, including the US$3.5m initial La Mata cash payment and US$0.2m Cerro La Mata signing payment.
Quarterly expenditure also included A$0.321m in staff costs and A$1.035m in administration and corporate costs.
Outlook and guidance
Updated Joaquin Mineral Resource Estimate and maiden integrated Joaquin–Cerro Leon PFS targeted for January 2027; RIGI inclusion remains targeted for 2H 2027.
Summer program plans 20,000m of resource-growth and extensional drilling across Joaquin and Cerro Leon; DFS targeted for end-2027.
Planned PFS work includes metallurgical and heap-leach testing, geotechnical and water studies, and Phase 2 baseline environmental studies for mining approvals.
Latest events from Unico Silver
- A 330 Moz AgEq resource base advances toward a January 2027 oxide PFS.USL
AGM 2026 - Resource base doubled, $75M raised, and development readiness achieved with $55M cash.USL
H2 2026 - Advancing 330 Moz AgEq silver resources toward production with a PFS due January 2027.USL
Investor presentation - 330Moz AgEq resource advances toward staged development, PFS, and production in 2026.USL
Noosa Mining Conference 2026 - High-grade drill results, strong cash position, and key land acquisition advance project de-risking.USL
Q4 2026 TU - Resource base surges to 330Moz AgEq, with robust funding and advancing development milestones.USL
Q3 2026 TU - Resource base expanded 16-fold, net loss narrowed, and $8M raised for exploration and acquisitions.USL
H2 2024 - Transformative year with major Argentine discoveries, $24M loss, and strong capital raises.USL
H2 2025 - 155% resource growth, strategic shift, and key resolutions drive strong development outlook.USL
AGM 2025