Vulcan Energy Resources (VUL) H2 2023 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2023 earnings summary
1 Nov, 2026Executive summary
Advanced Phase One to execution-ready status after a Bridging Engineering Study reduced estimated CAPEX and OPEX and simplified the project; construction and execution remain dependent on financing and permits.
Phase One targets 24,000 tonnes per year of lithium hydroxide monohydrate (LHM), alongside geothermal power and heat production from the same brine resource.
The operating geothermal plant generated 16,279 MWh of electricity in 2023, while commercial-scale lithium production remained under development.
Financial highlights
FY2023 revenue from continuing operations was €6.783m versus €3.622m in the six months ended 31 December 2022; the periods are not directly comparable.
Net loss after tax was €26.963m versus €13.450m for the six-month 2022 comparative; basic and diluted loss per share were €0.17 versus €0.09.
Cash and cash equivalents were €78.728m at year-end, down from €134.107m; net assets increased to €268.281m from €233.161m.
Operating and investing cash outflows were €24.331m and €92.460m, respectively; share issuance raised €67.350m gross during the year.
Revenue included €4.036m from electricity sales and €2.613m from drilling personnel outsourcing; outsourcing followed the acquisition of Comeback effective 1 February 2023.
Outlook and guidance
Phase One financing was targeted for completion in Q3 2024; the financing close is intended to trigger EPC and EPCM contract awards.
Construction of the integrated geothermal and lithium extraction plant was targeted to commence in H2 2024, subject to financing, permits and contract awards.
CLEOP commissioning and first LHM production were targeted for H2 2024; commercial production readiness is targeted for H2 2026.
The EIB advanced the project to “Under Appraisal” for proposed financing of up to €500m, subject to due diligence, credit approval, legal agreement and governing-body approval.
2024 priorities include first LHM to specification at CLEOP, Phase One financing, G-LEP construction and drilling at initial well sites.
Latest events from Vulcan Energy Resources
- Lionheart advances toward 2028–29 production with funding and price-protected offtakes.VUL
Q3 2026 - Lionheart Project financing secured, construction advanced, and net loss widened to €51.8m.VUL
H1 2026 - Project Ludwig PFS shows €1.7bn post-tax NPV8, 20.2% IRR, and 15% lower capital intensity.VUL
Status update - Fully funded lithium project in Europe targets low-cost, sustainable supply for battery makers.VUL
Corporate presentation - Financial close on €2.2bn funding enables major progress and de-risking for Lionheart Project.VUL
Q2 2026 - Fully funded lithium and renewable energy project targets lowest cost, scalable European supply.VUL
AGM 2026 presentation - Secured €2.2bn for Europe's largest integrated lithium project, with 2028 production targeted.VUL
Q1 2026 TU - Secured €2.2bn for Lionheart, began construction, and ended 2025 with €517.8m in cash.VUL
H2 2025 - Major grants, resource upgrades, and key contracts drive transformative project momentum.VUL
Q3 2025 TU