WA1 Resources (WA1) Q1 2027 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2027 TU earnings summary
27 Oct, 2026Executive summary
Luni advanced through integrated study and field programs toward a PFS targeted for Q4 CY2026; 2026 fieldwork exceeded PFS data requirements.
The quarter’s drilling continued to define high-grade niobium zones, while metallurgical results from the eastern focus area supported potential early mining plans.
Financial highlights
Quarter-end cash was $113.197m, compared with $123.799m at the start of the quarter.
Net operating cash used was $1.749m; net investing cash used was $8.728m and net financing cash used was $125k.
Exploration and evaluation expenditure was $10.654m; development expenditure was $464k.
A $2.4m research and development tax incentive was received during the quarter.
Outlook and guidance
Luni PFS remained on track for completion in Q4 CY2026; 2027 field and study programs are to be refined after the PFS.
Future drilling is planned to test potentially significant primary mineralisation in the deeper, unweathered zone.
2026 drilling is expected to improve confidence in high-grade resource zones and inform further metallurgical work and mining studies.
Latest events from WA1 Resources
- Luni PFS: 20,000 tpa FeNb, 17-year mine life and A$2.5bn pre-tax NPV.WA1
AGM 2026 presentation - Luni Niobium Project advanced with updated resources, strong cash, and narrowed FY26 net loss.WA1
H2 2026 - Luni is set to become a major global niobium supplier, reshaping critical mineral supply chains.WA1
Diggers & Dealers Mining Forum 2026 - Luni Niobium Project's resource and recovery advances, with $124M cash supporting Q4 PFS.WA1
Q4 2026 TU - Luni advances as a globally significant, high-grade niobium project with robust financial and technical progress.WA1
Corporate presentation - Luni drilling delivers high-grade results; $131M cash supports robust project advancement.WA1
Q3 2026 TU - Luni niobium discovery drives resource growth, robust funding, and technical milestones.WA1
H2 2024 - Luni Niobium Project delivered high-grade results, strong cash reserves, and secured Major Project Status.WA1
Q2 2026 TU - A world-class niobium discovery is advancing to diversify supply and meet critical mineral demand.WA1
Diggers & Dealers Mining Conference