WA1 Resources (WA1) investor relations material
WA1 Resources AGM 2026 presentation summary
Complete event summary combining all related documents: earnings call transcript, report, and slide presentation.PFS economics and project scale
Initial 17-year mine life; steady-state ferroniobium production of 20,000 tpa.
Base-case pre-tax NPV A$2.5bn (29% IRR) and post-tax NPV A$1.7bn (25% IRR); spot-case pre-tax NPV A$3.0bn.
Base-case average annual EBITDA A$479m at a 55% margin; life-of-mine EBITDA A$8.3bn and average AISC A$22,302/t FeNb.
Pre-tax payback 3.0 years from first production in the base case; 2.7 years in the spot case.
Total pre-production capital A$1.069bn, including A$770m for Luni and A$299m for Whyalla.
Reserve and operations
Probable Ore Reserve of 20.3Mt at 2.75% Nb₂O₅ underpins the initial mine life and represents ~25% of total Mineral Resources.
Mining is planned across eight stages from East Pit to West Pit, with sequencing designed to sustain high grades and optimise ore delivery.
Average mill throughput is 1.2Mtpa; beneficiation recovery 57.3%, concentrate grade 45.1% and average concentrate production 41,000 tpa.
Conversion plant metrics include 99.5% average refining recovery, 98.0% average conversion recovery and 20,000 tpa steady-state FeNb output.
Concentrate is planned to travel by road and rail to Whyalla via Alice Springs and Adelaide; a 110km haul road connects Luni to the existing road network.
Market and development pathway
Ferroniobium is used mainly as a micro-alloy in high-strength, low-alloy steel; structural, automotive and pipeline markets account for 47%, 28% and 17% of demand.
Two producers dominate global niobium output; Luni is positioned as a new large-scale, long-term supply source.
Schedule targets early 2029 commencement of works, early 2031 production, then ramp-up and steady-state operations.
Detailed feasibility work is advancing alongside funding pathway assessment; next phases include approvals, agreements, offtake and financing.
Further potential includes excess plant capacity, staged expansion, recovery optimisation, cost opportunities and value-added niobium products.
- Luni advances toward its Q4 PFS with $113.197m cash and strong high-grade results.WA1
Q1 2027 TU - Luni Niobium Project advanced with updated resources, strong cash, and narrowed FY26 net loss.WA1
H2 2026 - Luni is set to become a major global niobium supplier, reshaping critical mineral supply chains.WA1
Diggers & Dealers Mining Forum 2026 - Luni Niobium Project's resource and recovery advances, with $124M cash supporting Q4 PFS.WA1
Q4 2026 TU - Luni advances as a globally significant, high-grade niobium project with robust financial and technical progress.WA1
Corporate presentation - Luni drilling delivers high-grade results; $131M cash supports robust project advancement.WA1
Q3 2026 TU - Luni niobium discovery drives resource growth, robust funding, and technical milestones.WA1
H2 2024 - Luni Niobium Project delivered high-grade results, strong cash reserves, and secured Major Project Status.WA1
Q2 2026 TU - A world-class niobium discovery is advancing to diversify supply and meet critical mineral demand.WA1
Diggers & Dealers Mining Conference
)
)
)
)
)
)
)
)