Wallbridge Mining Company (WM) Corporate Presentation summary
Event summary combining transcript, slides, and related documents.
Corporate Presentation summary
23 Sep, 2025Project overview and resource base
Fenelon Gold Project PEA projects a 16-year mine life with average annual production of 107,000 oz, peaking at 127,000 oz in the first five years.
After-tax NPV (5%) is $706 million with a 21% IRR at a gold price of US$2,200/oz; initial capex is $579 million.
Fenelon 2025 MRE: 1.75 Moz indicated, 1.65 Moz inferred; Martiniere 2025 MRE: 346 Koz indicated, 387 Koz inferred.
The project leverages existing infrastructure and is located in a mining-friendly jurisdiction with access to clean energy.
Sensitivity analysis shows robust economics across a range of gold prices and cost scenarios.
Financial and operational highlights
Average annual free cash flow is projected at $120 million over the mine life.
Total cash cost is US$851/oz and all-in sustaining cost (AISC) is US$1,046/oz.
Sustaining capital over the life of mine is $449 million.
Payback period ranges from 2.4 to 5.7 years depending on gold price scenarios.
Free cash flow and NPV remain positive even with significant cost or gold price fluctuations.
Technical approach and infrastructure
Project phases include 2 years of pre-production and 16 years of production, with ramp and open-pit mining.
Metallurgical testing shows up to 96% overall gold recovery using gravity, CIL, and flotation.
Surface infrastructure includes a 120kV power line, camp, process plant, and tailings management facilities.
The PEA was developed using first principles and benchmarking against similar operations.
Study team includes InnovExplo, Norda Stelo, BBA Inc., and other specialized consultants.
Latest events from Wallbridge Mining Company
- Fenelon and Martiniere drive strong gold growth, robust economics, and expansion in Abitibi.WM
Corporate presentation7 Apr 2026 - Fenelon PEA projects 16 years of production, $706M NPV, and strong growth potential.WM
Corporate presentation19 Mar 2026 - Board changes, financials approved, and focus set on advancing key gold projects in Québec.WM
AGM 20243 Feb 2026 - High-grade Martinière drilling expands resources; updated estimate due Q1 2025.WM
Status Update15 Jan 2026 - All resolutions passed; gold projects advance with strong economics and expanded exploration.WM
AGM 20256 Jan 2026 - Phase II drilling at Martinière targets high-grade gold extensions and regional growth.WM
Status Update6 Jan 2026 - Fenelon’s robust PEA and Martiniere’s exploration success drive strong growth prospects.WM
Investor Update6 Jan 2026 - New PEA for Fenelon targets 16-year underground mine; Martinière drilling expands potential.WM
2025 Precious Metals Summit Beaver Creek Conference16 Dec 2025 - Fenelon Gold Project PEA projects $706M NPV, 21% IRR, and 2.1 Moz indicated resources.WM
Corporate Presentation23 Sep 2025