Westwater Resources (WWR) Q3 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 earnings summary
12 Nov, 2026Executive summary
Kellyton construction, equipment procurement and customer qualification advanced alongside Coosa permitting and mine planning.
Phase I cost estimate remained $245 million, with $136 million incurred by Sept. 30; completion and commissioning depend on additional financing.
Q3 net loss narrowed to $4.4 million from $9.8 million YoY, primarily reflecting lower convertible-note losses.
Financial highlights
Q3 2026 net loss was $4.4 million, or $0.03 per share, versus $9.8 million, or $0.12 per share, in Q3 2025.
9M 2026 net loss was $13.4 million, or $0.11 per share, versus $16.4 million, or $0.21 per share, in 9M 2025.
Q3 improvement from lower convertible-note losses was partly offset by higher Coosa permitting, consulting and outside-services costs; 9M gains also included higher interest income.
Operating expenses were $4.599 million in Q3 2026 versus $4.080 million YoY, and $13.601 million in 9M 2026 versus $10.290 million.
Outlook and guidance
Kellyton Phase I cost estimate remained $245 million, including $14.8 million for contingency and potential escalation; $136 million had been incurred through Sept. 30.
Management expects Phase I capacity of 12,500 metric tons/year of CSPG to be fully committed under offtake before commissioning; construction completion and operations depend on additional funding.
FAST-41 dashboard targets Coosa environmental review and permitting completion in June 2027, subject to agency review; a mine-development feasibility study is planned for 2027.
Current cash was expected to cover working capital and planned non-discretionary capital expenditures beyond a year after statement issuance, but not full Phase I completion.
Latest events from Westwater Resources
- Advancing US-based battery-grade graphite production with strong federal support and market demand.WWR
Corporate presentation - EXIM's $25M loan advances Kellyton toward U.S. battery-grade graphite production in 2027; more funding needed.WWR
Q2 2026 - Net loss increased as construction slowed and customer contracts ended, but liquidity remains solid.WWR
Q1 2026 - Proxy seeks approval for director elections, equity plan, share increase, and convertible note conversion.WWR
Proxy filing - Advancing US-based battery-grade graphite production with strong demand and project economics.WWR
Corporate presentation - Advancing US-based battery-grade graphite production with secured offtake and vertical integration.WWR
Corporate presentation - Advancing U.S. graphite anode production with secured contracts and strong market tailwinds.WWR
Corporate presentation - Six key proposals, including equity plan and share authorization, up for virtual vote in 2026.WWR
Proxy filing - Kellyton and Coosa progress, strong demand, and $48.6M cash highlight U.S. graphite leadership.WWR
Q4 2025