19 Oct, 2026Executive summary
DFS confirmed Kokoseb’s technical and economic viability: 14-year mine life and 1,836koz total production, averaging 150koz annually over the first 10 years.
A 29% MRE increase to 3.78Moz Au and a maiden Probable Ore Reserve of 1.95Moz underpin development planning.
Placement proceeds, proposed Sprott financing and existing cash are expected to fund construction through first gold, targeted for Q4 2028.
Financial highlights
DFS base case at US$3,600/oz: post-tax NPV5% US$1,214m, IRR 41%, payback 21 months and post-tax LOM free cash flow US$1,914m.
Spot case at US$4,075/oz: post-tax NPV5% US$1,577m, IRR 49%, payback 17 months and post-tax LOM free cash flow US$2,442m.
Pre-production capital estimate US$475m; includes US$50m for strategic water and power infrastructure supporting potential expansion optionality.
Quarter-end cash A$229.2m, no debt; quarterly operating cash inflow A$66k and investing cash outflow A$7.141m, including A$7.103m exploration and evaluation spend.
Outlook and guidance
Early works targeted for H1 2027, subject to key approvals and definitive financing; first gold targeted for Q4 2028.
Indicative Sprott financing close targeted for Q4 2026; financing remains subject to due diligence, definitive documents, investment committee approval and receipt of key permits.
Execution readiness includes owner’s team formation, FEED, project approvals and preparation for long-lead procurement.
Further drilling to test underground resource potential is expected over the next 6–12 months, depending on results and exploration priorities.
Latest events from WIA Gold
- Kokoseb Project fully funded and permitted, targeting first gold in Q4 2028 after robust DFS.WIA
H2 2026 - Fully funded with US $1.2B NPV, 41% IRR, and strong growth potential.WIA
Investor update - DFS on track, high-grade resource expanded, A$92M raised, and strong cash position maintained.WIA
Q4 2026 TU - Kokoseb advances as a major gold project with 2.93 Moz resource and strong economic metrics.WIA
Corporate presentation - DFS on track, strong cash, high-grade results, and Côte d'Ivoire divestment completed.WIA
Q3 2026 TU - Kokoseb resource up 63% to 2.12 Moz; $27.8M raised; cash at $15.05M; net loss $3.61M.WIA
H2 2024 - Kokoseb resource up 38% to 2.93 Moz; $30M raised post-year-end for project advancement.WIA
H2 2025 - Kokoseb advances with strong economics; Côte d'Ivoire divested, A$30m raised for exploration.WIA
H1 2026 - Kokoseb advances as a major Namibian gold project with 2.93Moz resource and strong economics.WIA