Boab Metals (BML) Q4 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2026 TU earnings summary
30 Jul, 2026Executive summary
Significant progress made on Sorby Hills development, with engineering, commercial, and construction activities advancing as scheduled.
EPC contract executed for $109M to relocate and refurbish DeGrussa Processing Plant; acquisition completed.
Six-year diesel supply agreement secured to ensure reliable fuel for construction and operations.
Early works and bulk earthworks completed on budget, with construction tracking ahead of schedule.
First concentrate production remains on track for H2 2027.
Financial highlights
Cash balance at 30 June 2026 was A$60.2 million.
Net cash from operating activities for the quarter was A$144k; year-to-date operating cash outflow was A$1.92M.
Net cash used in investing activities for the quarter was A$27.74M; year-to-date investing outflow was A$46.12M.
Net cash used in financing activities for the quarter was A$9.96M; year-to-date financing inflow was A$100.74M.
Outlook and guidance
Project Delivery Plan to be released in the September quarter, updating economics and Ore Reserves in response to higher silver prices.
Stage 2 of the Mining Camp, mining contract award, and reconstruction of the DeGrussa Plant scheduled for next quarter.
Ongoing drilling and exploration expected to support mine life extension and resource growth.
Latest events from Boab Metals
- Advanced Sorby Hills toward FID with key milestones, improved cash, and robust project economics.BML
H2 202525 Mar 2026 - Sorby Hills project advances with improved economics, reduced loss, and path to 100% ownership.BML
H2 202425 Mar 2026 - Sorby Hills fully funded and construction underway, with cash reserves at $89.9 million.BML
H1 202615 Mar 2026 - FEED Study shows strong project economics, reduced costs, and solid funding position.BML
Q4 2024 TU29 Jan 2026 - Sorby Hills targets near-term production with strong silver leverage and first quartile costs.BML
Corporate presentation29 Jan 2026 - Sorby Hills offers a large, low-cost, silver-leveraged resource nearing production.BML
Corporate presentation29 Jan 2026 - Option secured for 100% Sorby Hills ownership; strong project economics and cash of A$4.35M.BML
Q1 2025 TU29 Jan 2026 - Low-cost, high-grade lead-silver project targets 2025 FID with strong economics and Trafigura backing.BML
Corporate presentation29 Jan 2026 - FEED Study confirms strong economics and full project control, with silver price driving upside.BML
AGM 2024 presentation29 Jan 2026