Boab Metals (BML) Q4 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2026 TU earnings summary
30 Jul, 2026Executive summary
Significant progress made on Sorby Hills development, with engineering, commercial, and construction activities advancing as scheduled.
EPC contract executed for $109M to relocate and refurbish DeGrussa Processing Plant; acquisition completed.
Six-year diesel supply agreement secured to ensure reliable fuel for construction and operations.
Early works and bulk earthworks completed on budget, with construction tracking ahead of schedule.
First concentrate production remains on track for H2 2027.
Financial highlights
Cash balance at 30 June 2026 was A$60.2 million.
Net cash from operating activities for the quarter was A$144k; year-to-date operating cash outflow was A$1.92M.
Net cash used in investing activities for the quarter was A$27.74M; year-to-date investing outflow was A$46.12M.
Net cash used in financing activities for the quarter was A$9.96M; year-to-date financing inflow was A$100.74M.
Outlook and guidance
Project Delivery Plan to be released in the September quarter, updating economics and Ore Reserves in response to higher silver prices.
Stage 2 of the Mining Camp, mining contract award, and reconstruction of the DeGrussa Plant scheduled for next quarter.
Ongoing drilling and exploration expected to support mine life extension and resource growth.
Latest events from Boab Metals
- Sorby Hills construction is underway, with first ore targeted for H2 2027 and $60.9m cash on hand.BML
H2 2026 - Fully funded project targets 2027 production with extended mine life and strong economics.BML
Mining Forum Americas 2026 - Construction of a major silver-lead project is underway, targeting production in H2 2027.BML
Corporate presentation - Advanced Sorby Hills toward FID with key milestones, improved cash, and robust project economics.BML
H2 2025 - Sorby Hills project advances with improved economics, reduced loss, and path to 100% ownership.BML
H2 2024 - Sorby Hills fully funded and construction underway, with cash reserves at $89.9 million.BML
H1 2026 - FEED Study shows strong project economics, reduced costs, and solid funding position.BML
Q4 2024 TU - Sorby Hills targets near-term production with strong silver leverage and first quartile costs.BML
Corporate presentation - Sorby Hills offers a large, low-cost, silver-leveraged resource nearing production.BML
Corporate presentation