10 Sep, 2026Executive summary
Significant progress in the Mako Gas Project, including Final Investment Decision (FID) and execution of key commercial, technical, and funding milestones.
Project fully funded through a farm-down of 75% participating interest to Nations Natuna Barat (NNB), with NNB covering development capex.
First-time booking of 1P and 2P reserves for Mako; first gas targeted for 4Q 2027.
Leadership restructure with CEO transition and expanded Executive Chairman mandate.
Financial highlights
Consolidated profit after tax for H1 2026 was US$8.59 million, reversing a US$2.40 million loss in H1 2025.
Total assets increased to US$102.72 million (from US$44.90 million at end-2025), mainly due to Mako project investment and Coro acquisition.
Oil and gas assets under development rose to US$66.22 million (from US$28.42 million at end-2025).
Cash and cash equivalents increased to US$3.26 million (from US$1.36 million at end-2025).
Net cash used in operating activities was US$11.04 million; investing activities used US$17.80 million; financing activities generated US$30.75 million.
Outlook and guidance
Mako Gas Project remains on track for first gas in 4Q 2027.
Total project capex estimated at US$320 million, unchanged from prior guidance.
Project is fully funded, including contingency, with over 90% of capital contracts awarded.
Ongoing discussions for minority farm-in to Aceh assets.
Latest events from Conrad Asia Energy
- Mako field fully funded to production, with major resource upside in Indonesia.CRD
Investor presentation - Mako Gas Project remains fully funded and on track for first gas in Q4 2027, with major contracts secured.CRD
Q2 2026 - Transformative Mako funding secured; first gas on track for Q4 2027 amid tight cash position.CRD
H2 2025 - Mako Gas Project fully funded and on track for first gas in Q4 2027, driving strong cash flow.CRD
Investor presentation - Major Indonesian gas assets advance toward production and commercialisation, targeting regional demand.CRD
Investor Presentation - Advancing major Southeast Asian gas projects with strong resource base and commercialisation progress.CRD
Investor Presentation - All AGM resolutions passed with strong support; Mako Gas Project fully funded and on track.CRD
AGM 2026 - Fully funded Mako Gas Project targets first gas in Q4 2027, driving strong future cash flow.CRD
Corporate presentation - All Mako gas volumes allocated via GSAs; project FID delayed, cash at US$4.11M, funding secure.CRD