Conrad Asia Energy (CRD) Q2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2026 earnings summary
26 Jul, 2026Executive summary
Over 90% of Mako Gas Project capital contracts, totaling over US$290 million, have been awarded, with total project costs estimated at US$320 million, unchanged from prior guidance.
The project is fully funded and on track for first gas in Q4 2027.
Significant infrastructure progress includes the completion of the "hot tap" connection to the Pemping gas pipeline, enabling delivery to Indonesia's domestic market.
Leadership restructure announced: CEO stepping back, Executive Chairman appointed, and CEO search underway.
Financial highlights
Closing cash at 30 June 2026 was US$3.26 million.
Net cash used in operating activities for the quarter was US$2.36 million; net cash used in investing activities was US$17.28 million.
Net cash from financing activities was US$17.61 million, mainly from drawdowns under the Carry Loan Agreement.
Total funds drawn under the Carry Loan Agreement at quarter-end were US$38.97 million.
Payments to related parties during the quarter totaled US$0.54 million.
Outlook and guidance
First gas from the Mako Gas Project remains targeted for Q4 2027.
Project costs and funding remain in line with previous guidance, with sufficient financing facilities in place.
Estimated available funding covers 1.39 quarters of operations, expected to normalize to 2.17 quarters after adjusting for one-off items.
Latest events from Conrad Asia Energy
- Mako field fully funded to production, with major resource upside in Indonesia.CRD
Investor presentation27 Jul 2026 - Transformative Mako funding secured; first gas on track for Q4 2027 amid tight cash position.CRD
H2 202524 Jul 2026 - All Mako gas volumes allocated via GSAs; project FID delayed, cash at US$4.11M, funding secure.CRD
H2 202424 Jul 2026 - Mako Gas Project fully funded and on track for first gas in Q4 2027, driving strong cash flow.CRD
Investor presentation30 Jun 2026 - Major Indonesian gas assets advance toward production and commercialisation, targeting regional demand.CRD
Investor Presentation25 Jun 2026 - Advancing major Southeast Asian gas projects with strong resource base and commercialisation progress.CRD
Investor Presentation25 Jun 2026 - All AGM resolutions passed with strong support; Mako Gas Project fully funded and on track.CRD
AGM 202616 Jun 2026 - Fully funded Mako Gas Project targets first gas in Q4 2027, driving strong future cash flow.CRD
Corporate presentation4 Jun 2026 - Mako Gas Project FID achieved, reserves booked, and development fully funded for first gas in 2027.CRD
Q1 202629 Apr 2026