Conrad Asia Energy (CRD) H2 2025 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2025 earnings summary
24 Jul, 2026Executive summary
Secured a transformative farm-in and funding agreement for the Mako gas field, with Nations Natuna Barat acquiring a 75% non-operated interest and providing 100% of project development costs and working capital, fully carrying Conrad's 25% interest through to commercial production, subject to government approvals.
Signed a binding settlement with Empyrean Energy, resolving historical cash call arrears and consolidating project interests, with Empyrean transferring its 8.5% interest to Conrad and forming a new SPV structure.
Mako project remains on track for first gas in Q4 2027, with all major funding and partner alignment milestones achieved.
Financial highlights
Closing cash at 31 December 2025 was US$1.36 million.
Net cash used in operating activities for the quarter was US$1.24 million; net cash used in investing activities was US$7.26 million, mainly due to a US$7.2 million advance payment for Mako project equipment.
Net cash from financing activities was US$7.03 million, including a US$7.2 million drawdown from the Carry Loan Agreement (CLA).
Estimated quarters of funding available at period end was 0.16, but excluding the one-time compressor payment and with anticipated receipts from NNB, funding is expected to be sufficient.
Outlook and guidance
First gas from Mako is targeted for Q4 2027, with project execution now underway and all financing secured.
Anticipates receipt of US$5 million from NNB in the next quarter, with further tranches of US$4 million and US$7 million expected by Q3 2026 and Q4 2027, respectively.
Ongoing discussions with potential equity partners for Aceh assets and further seismic and development activities planned.
Latest events from Conrad Asia Energy
- Mako field fully funded to production, with major resource upside in Indonesia.CRD
Investor presentation27 Jul 2026 - Mako Gas Project remains fully funded and on track for first gas in Q4 2027, with major contracts secured.CRD
Q2 202626 Jul 2026 - All Mako gas volumes allocated via GSAs; project FID delayed, cash at US$4.11M, funding secure.CRD
H2 202424 Jul 2026 - Mako Gas Project fully funded and on track for first gas in Q4 2027, driving strong cash flow.CRD
Investor presentation30 Jun 2026 - Major Indonesian gas assets advance toward production and commercialisation, targeting regional demand.CRD
Investor Presentation25 Jun 2026 - Advancing major Southeast Asian gas projects with strong resource base and commercialisation progress.CRD
Investor Presentation25 Jun 2026 - All AGM resolutions passed with strong support; Mako Gas Project fully funded and on track.CRD
AGM 202616 Jun 2026 - Fully funded Mako Gas Project targets first gas in Q4 2027, driving strong future cash flow.CRD
Corporate presentation4 Jun 2026 - Mako Gas Project FID achieved, reserves booked, and development fully funded for first gas in 2027.CRD
Q1 202629 Apr 2026