Conrad Asia Energy (CRD) Q3 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 TU earnings summary
27 Oct, 2026Executive summary
Mako advanced into full-scale fabrication; over 90% of capital contract commitments are signed or awarded, with first gas still targeted for Q4 2027.
The 75% Duyung PSC farm-down to Nations completed after regulatory approval and receipt of the second US$4m consideration tranche; WNEL retained a 25% interest and operatorship.
Financial highlights
Mako total capex to first gas remains US$320m (100% basis), including WNEL’s 25% share of approximately US$80m; the project is fully funded with substantial contingency.
Future Mako operating costs are estimated at US$70–80m per annum (100% basis), including pipeline transportation.
Quarter-end cash was US$6.653m; net operating cash outflow was US$1.890m and net investing cash outflow was US$13.661m.
Development capex payments were US$15.362m in the quarter; compressor advances were US$2.157m.
Outlook and guidance
First gas remains on track for Q4 2027; Mako remains on schedule and budget, with total capex guidance unchanged at US$320m.
MOPU conversion remains on schedule; CSF and SURF work is progressing, with SURF site fabrication planned for mid-Q4 2026.
WNEL is expected to draw a further approximately US$10.75m under the Carry Loan Agreement in the next quarter for its Mako development costs.
BPMA and Conrad discussed potential completion of the Meulaboh and Singkil development plans during 2027, subject to evaluation and subsequent decisions.
Latest events from Conrad Asia Energy
- Fully funded Mako targets Q4 2027 first gas, with Aceh offering substantial resource upside.CRD
Investor presentation - Mako Gas Project fully funded and on track for 4Q 2027 first gas, with strong H1 2026 profit.CRD
H1 2026 - Mako field fully funded to production, with major resource upside in Indonesia.CRD
Investor presentation - Mako Gas Project remains fully funded and on track for first gas in Q4 2027, with major contracts secured.CRD
Q2 2026 TU - Transformative Mako funding secured; first gas on track for Q4 2027 amid tight cash position.CRD
H2 2025 - Mako Gas Project fully funded and on track for first gas in Q4 2027, driving strong cash flow.CRD
Investor presentation - Major Indonesian gas assets advance toward production and commercialisation, targeting regional demand.CRD
Investor Presentation - Advancing major Southeast Asian gas projects with strong resource base and commercialisation progress.CRD
Investor Presentation - All Mako gas volumes allocated via GSAs; project FID delayed, cash at US$4.11M, funding secure.CRD
H2 2024