Conrad Asia Energy (CRD) Q3 2026 TU earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Conrad Asia Energy Ltd

Q3 2026 TU earnings summary

27 Oct, 2026

Executive summary

  • Mako advanced into full-scale fabrication; over 90% of capital contract commitments are signed or awarded, with first gas still targeted for Q4 2027.

  • The 75% Duyung PSC farm-down to Nations completed after regulatory approval and receipt of the second US$4m consideration tranche; WNEL retained a 25% interest and operatorship.

Financial highlights

  • Mako total capex to first gas remains US$320m (100% basis), including WNEL’s 25% share of approximately US$80m; the project is fully funded with substantial contingency.

  • Future Mako operating costs are estimated at US$70–80m per annum (100% basis), including pipeline transportation.

  • Quarter-end cash was US$6.653m; net operating cash outflow was US$1.890m and net investing cash outflow was US$13.661m.

  • Development capex payments were US$15.362m in the quarter; compressor advances were US$2.157m.

Outlook and guidance

  • First gas remains on track for Q4 2027; Mako remains on schedule and budget, with total capex guidance unchanged at US$320m.

  • MOPU conversion remains on schedule; CSF and SURF work is progressing, with SURF site fabrication planned for mid-Q4 2026.

  • WNEL is expected to draw a further approximately US$10.75m under the Carry Loan Agreement in the next quarter for its Mako development costs.

  • BPMA and Conrad discussed potential completion of the Meulaboh and Singkil development plans during 2027, subject to evaluation and subsequent decisions.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Conrad Asia Energy