Element 25 (E25) Q2 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2026 TU earnings summary
27 Jan, 2026Executive summary
Advanced Butcherbird Expansion Project (BBX) towards construction, targeting 1.1Mtpa manganese concentrate production for steel and battery markets.
Secured AU$10M equity placement and AU$50M senior debt facility from NAIF to fund BBX.
Finalised key equipment procurement and advanced offtake and mining services contract negotiations.
Progressed HPMSM refinery project in Louisiana, supported by US$166M DoE grant and US$115M from GM and Stellantis.
Financial highlights
Net cash used in operating activities for the quarter: AU$941,000; for six months: AU$1,474,000.
Net cash used in investing activities for the quarter: AU$1,423,000; for six months: AU$2,515,000.
Net cash from financing activities for the quarter: AU$9,605,000 (mainly from equity placement).
Cash and cash equivalents at quarter end: AU$7,774,000.
Outlook and guidance
BBX project schedule on track, with commissioning and commercial production targeted for 2027.
HPMSM refinery in Louisiana expected to supply US EV battery market, with further facilities planned under a hub-and-spoke model.
Latest events from Element 25
- Butcherbird expansion and US HPMSM project advance on schedule with robust funding and DOE support.E25
Q4 2026 TU - Butcherbird expansion and HPMSM refinery advance, with funding and contracts on track.E25
Q3 2026 TU - Butcherbird expansion and US HPMSM project advanced, despite FY24 revenue and margin declines.E25
H2 2024 - Expansion and US battery materials facility advanced, with improved loss and strong funding.E25
H1 2026 - Expanding Australian manganese mine and US refinery target global battery and steel markets.E25
Investor presentation - US$166M DOE grant, AU$50M NAIF debt, and resource upgrades drive future growth.E25
H2 2025 - Raised AU$10M equity, secured AU$50M debt, and advanced global HPMSM projects; cash AU$10.19M.E25
Q1 2026 TU - AU$50M NAIF debt and US$166M DoE grant drive BBX and HPMSM project growth.E25
Q4 2025 TU - Major mine and U.S. refinery expansion advance to meet surging EV battery manganese demand.E25