Investor presentation
Logotype for FireFly Metals Ltd

FireFly Metals (FFM) Investor presentation summary

Event summary combining transcript, slides, and related documents.

Logotype for FireFly Metals Ltd

Investor presentation summary

19 Oct, 2026

Resource and growth

  • Green Bay resource totals 60.2Mt at 2.4% CuEq Measured & Indicated and 23.5Mt at 2.5% CuEq Inferred; 72% is in the higher-confidence M&I category.

  • High-grade core totals 18.1Mt at 4.3% CuEq M&I and 7.0Mt at 4.4% CuEq Inferred; deepest reported hole graded 49m at 6.1% CuEq.

  • The 346km² district land package includes 325+ drill targets, with less than 5% tested; six underground and two surface rigs are operating.

  • FY27 regional exploration budget is A$16.7M, targeting Ming extensions, historic VMS mines, Tilt Cove, Nugget Pond and Little Deer.

PEA economics

  • The 1.8Mtpa case forecasts a 32-year mine life, post-tax NPV at 7% of ~A$2.2B, IRR of ~41%, and post-tax LOM free cash flow of ~A$5.3B.

  • The 1.8Mtpa case targets peak production of ~50ktpa CuEq; initial capital is ~A$514M and C3 cash cost is US$2.34/lb CuEq.

  • The 4.6Mtpa case forecasts a 22-year mine life, post-tax NPV at 7% of ~A$3.0B, IRR of ~39%, and post-tax LOM free cash flow of ~A$6.5B.

  • The 4.6Mtpa case targets ~100ktpa CuEq peak production; expansion capital is ~A$484M and C3 cash cost is US$2.17/lb CuEq.

  • The 4.6Mtpa expansion is expected to be substantially funded from cash flow generated by the 1.8Mtpa base case.

Funding and development

  • Pro forma cash and liquid assets are ~A$368M, with no debt or streams; initial debt advice indicates capacity above US$350M (~A$500M) for the 1.8Mtpa case.

  • Financing discussions with tier 1 banks, potential offtake partners, export credit agencies and other lenders have included conditional, non-binding indicative terms.

  • Early works began in April 2026, including underground development, additional ventilation and power, exploration platforms, camp expansion and water-treatment upgrades.

  • Indicative milestones: DFS in Q1 2027, debt and offtake in Q2 2027, FID in mid-2027 and first copper production in 2029.

Partial view of Summaries dataset, powered by Quartr API