G Mining Ventures (GMIN) Investor update summary
Event summary combining transcript, slides, and related documents.
Investor update summary
13 Nov, 2026Mine and process plant construction
Mine Maintenance Facility exterior, warehouse and offices complete; overhead crane commissioned in October, with oil distribution system next on the critical path.
Truck Wash Bay earthworks and foundations complete; structural rebar work continuing through November. Fuel Bay foundation complete, with work continuing through November.
HFO and LFO fuel storage foundations complete; Unloading Station foundation and structure complete, with piping and electrical work advancing significantly.
CIP tanks more than 85% complete, with the last tank underway in November; CIL tanks ~20% erected and connecting pipe rack complete.
SAG Mill shell installation began in late October; completion of the four-piece shell and heads targeted for early December.
Mine and site infrastructure
Primary Crusher first floor complete and wall construction ongoing; MSE wall earthworks complete and ready for the next phase.
Ore Reclaim Tunnel approach slab and mat foundation complete; conveyor support columns being placed through November.
TSF clearing, grubbing, alluvial material removal and engineered fill placement ongoing; October target met and work progressing according to plan.
Oko-Ghanie Quarry Pit on schedule and providing competent rock for mobile-crusher aggregate production; drilling and blasting continue.
ROM pad dumping underway to prepare for ore feed; Oko West diversion ditch and clearing works progressing.
Logistics, camp and community
Wharf Landing passenger dock structural framing nearly complete; fuel storage tanks and transfer piping underway, with Truck Shop foundation complete and Warehouse foundation started.
A 60-metre containerized barge is under construction by Guyana Port Inc.; designed to carry 8 to 20-foot containers on the Demerara and Mazaruni rivers to Wharf Landing.
Camp El Dorado Dorms B and C complete, Dorm A and groundworks advancing on schedule; Sports Complex construction started.
Fifth community education forum of 2026 held in Region Seven, covering jobs, training, local procurement and ESG commitments.
October activities included a breast cancer awareness session at Camp El Dorado and employee and family participation in Georgetown’s Pinktober Walk/Run.
Latest events from G Mining Ventures
- Higher-grade ore lifted Q3 output and cash flow as Oko advanced toward H2 2027 first gold.GMIN
Q3 2026 - Tocantinzinho cash flow is supporting Oko’s path to ~500 koz of annual production potential.GMIN
Corporate presentation - Oko West nears first gold as exploration and expansion target 1M oz annual output.GMIN
Mining Forum Americas 2026 - On track for >500 koz gold production by 2028, fueled by Oko West and strong cash flow.GMIN
AGM 2026 presentation - Strong Q2 2026 results, record free cash flow, and major project progress amid higher cost guidance.GMIN
Q2 2026 - Transformational gold production growth to 700,000 oz by 2028, led by Tier-1 projects.GMIN
Corporate presentation - Significant construction progress and strategic acquisition drive project advancement and workforce unity.GMIN
Corporate presentation - On track for 500,000+ oz annual gold production by 2028, driven by flagship projects and exploration.GMIN
Corporate presentation - Record gold output, low costs, and major project milestones drive robust 2024 results and 2025 outlook.GMIN
Q4 2024