Logotype for G Mining Ventures Corp

G Mining Ventures (GMIN) Investor update summary

Event summary combining transcript, slides, and related documents.

Logotype for G Mining Ventures Corp

Investor update summary

13 Nov, 2026

Mine and process plant construction

  • Mine Maintenance Facility exterior, warehouse and offices complete; overhead crane commissioned in October, with oil distribution system next on the critical path.

  • Truck Wash Bay earthworks and foundations complete; structural rebar work continuing through November. Fuel Bay foundation complete, with work continuing through November.

  • HFO and LFO fuel storage foundations complete; Unloading Station foundation and structure complete, with piping and electrical work advancing significantly.

  • CIP tanks more than 85% complete, with the last tank underway in November; CIL tanks ~20% erected and connecting pipe rack complete.

  • SAG Mill shell installation began in late October; completion of the four-piece shell and heads targeted for early December.

Mine and site infrastructure

  • Primary Crusher first floor complete and wall construction ongoing; MSE wall earthworks complete and ready for the next phase.

  • Ore Reclaim Tunnel approach slab and mat foundation complete; conveyor support columns being placed through November.

  • TSF clearing, grubbing, alluvial material removal and engineered fill placement ongoing; October target met and work progressing according to plan.

  • Oko-Ghanie Quarry Pit on schedule and providing competent rock for mobile-crusher aggregate production; drilling and blasting continue.

  • ROM pad dumping underway to prepare for ore feed; Oko West diversion ditch and clearing works progressing.

Logistics, camp and community

  • Wharf Landing passenger dock structural framing nearly complete; fuel storage tanks and transfer piping underway, with Truck Shop foundation complete and Warehouse foundation started.

  • A 60-metre containerized barge is under construction by Guyana Port Inc.; designed to carry 8 to 20-foot containers on the Demerara and Mazaruni rivers to Wharf Landing.

  • Camp El Dorado Dorms B and C complete, Dorm A and groundworks advancing on schedule; Sports Complex construction started.

  • Fifth community education forum of 2026 held in Region Seven, covering jobs, training, local procurement and ESG commitments.

  • October activities included a breast cancer awareness session at Camp El Dorado and employee and family participation in Georgetown’s Pinktober Walk/Run.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from G Mining Ventures