Corporate presentation
Logotype for Lithium Americas Corp

Lithium Americas (LAC) Corporate presentation summary

Event summary combining transcript, slides, and related documents.

Logotype for Lithium Americas Corp

Corporate presentation summary

21 May, 2026

Project overview and strategy

  • Thacker Pass is the largest lithium project in the U.S., targeting 40,000 t/y battery-grade lithium carbonate in Phase 1, with expansion potential up to 160,000 t/y across five phases and an estimated 85-year mine life.

  • Mechanical completion of Phase 1 is targeted for late 2027, with commercial production ramping up in 2028; detailed engineering is over 95% complete and early commissioning expected in Q4 2026.

  • The project is a joint venture: 62% owned by the company and 38% by General Motors, which has a 20-year offtake agreement for up to 100% of Phase 1 and 38% of Phase 2 production.

  • Thacker Pass is located in Nevada, considered the top global jurisdiction for mineral investment, with strong government and community support.

  • The project is vertically integrated, using proven processing technology and standard equipment, with no novel processes required.

Financials and funding

  • Phase 1 construction is fully funded through a $2.23 billion U.S. Department of Energy loan, $945 million from General Motors, and $250 million from Orion Resource Partners.

  • As of March 31, 2026, $1.14 billion had been spent on construction, with 2026 capex guidance of $1.3–$1.6 billion.

  • The DOE loan is at the U.S. Treasury rate with a 23-year tenor and includes a five-year debt service deferral.

  • The project’s C1 operating cost is $6,238/t LCE for Years 1–25, positioning it competitively even during lithium price downturns.

Construction and operational progress

  • Over 2.43 million workhours have been completed without a serious injury; over 1,065 personnel are on site, expected to exceed 2,000 at peak construction.

  • More than 75% of structural steel is in transit or on site, with key equipment deliveries ongoing and regional substation upgrades completed ahead of schedule.

  • The processing plant area is approximately 1,100 ft x 3,100 ft, with major facilities including beneficiation, sulfuric acid, and crystallization plants.