Lithium Americas (LAC) Q2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2026 earnings summary
12 Nov, 2026Executive summary
Developing Thacker Pass in Nevada through a GM joint venture; 62% owned and managed, with GM holding 38% and DOE holding a 5% JV warrant.
Construction accelerated, with over 1,600 workers on site, detailed engineering over 95% complete and procurement over 80%; mechanical completion targeted for late 2027 and ramp-up in 2028.
Phase 1 is designed for 40,000 tonnes/year of battery-quality lithium carbonate production.
No operating revenue yet; future profitability depends on successful project completion and continued financing.
Financial highlights
Net income was $6.3 million for the first half of 2026 versus a $24.8 million loss in 2025; Q2 net income was $1.7 million versus a $13.2 million loss.
Cash and restricted cash totaled $1,279.2 million at June 30, 2026, up from $905.6 million at year-end 2025, including $530.3 million at the JV.
G&A expenses rose to $26.2 million for the first half of 2026 from $14.4 million a year earlier, reflecting hiring, compensation and expanded operations.
Total assets increased to $3,535.9 million at June 30, 2026, from $2,579.0 million at year-end 2025.
Net cash used in investing activities was $631.6 million in the first half, primarily reflecting Thacker Pass construction spending.
Outlook and guidance
Thacker Pass Phase 1 mechanical completion remains targeted for late 2027, with production ramp-up in 2028.
Fiscal 2026 Phase 1 capex guidance is $1.3–$1.6 billion.
Early commissioning of utilities and completion of main concrete work are expected in the second half of 2026.
A definitive Thacker Pass capital estimate is targeted by the end of Q3 2026.
Liquidity is expected to be sufficient for at least 12 months, with further funding needs anticipated before production begins.
Latest events from Lithium Americas
- Late-2027 completion target, $3.83B capex estimate and expansion potential to 160,000 t/y.LAC
Corporate presentation - Fair-value gains lifted Q3 profit as Thacker Pass Phase 1 capex rose to $3.83B.LAC
Q3 2026 - Thacker Pass is set to deliver major U.S. lithium capacity with full funding and rapid construction progress.LAC
Corporate presentation - Thacker Pass is set to boost U.S. lithium supply with fully funded, large-scale production by 2028.LAC
Corporate presentation - Q1 2026 marked a return to profit, strong liquidity, and rapid Thacker Pass project advancement.LAC
Q1 2026 - Shareholders to vote on board size, director elections, and auditor appointment at the annual meeting.LAC
Proxy filing - 2025 marked pivotal progress at Thacker Pass, with robust governance and performance-driven compensation.LAC
Proxy filing - Shareholders to vote on Board, auditor, and expanded equity plan after a transformative year.LAC
Proxy filing - Thacker Pass construction advances with strong funding and workforce ramp-up to meet U.S. lithium demand.LAC