Lithium Americas (LAC) Q4 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2025 earnings summary
19 Mar, 2026Executive summary
Construction at Thacker Pass advanced rapidly in 2025, with mechanical completion of Phase 1 targeted for late 2027 and peak construction activity expected in 2026.
Workforce expansion is underway, with approximately 1,800 skilled craftspeople anticipated on site by late 2026.
The project is positioned to play a central role in U.S. energy and national security by strengthening domestic lithium supply chains.
Financial highlights
As of December 31, 2025, total cash and restricted cash stood at $905.6 million, including $412.6 million at the Thacker Pass JV level.
$611.6 million in construction and project-related costs were capitalized in 2025, totaling $982.8 million to date.
Net loss for 2025 was $86.3 million, up from $42.6 million in 2024, with a loss per share of $0.50 compared to $0.21 in the prior year.
Total assets increased to $2,579.0 million, and total long-term liabilities rose to $815.6 million as of year-end 2025.
Outlook and guidance
Capex guidance for Thacker Pass Phase 1 in 2026 is $1.3–$1.6 billion, unchanged from previous guidance.
Mechanical completion of Phase 1 remains on track for late 2027, with detailed engineering 93% complete and procurement 60% complete as of year-end 2025.
Latest events from Lithium Americas
- Shareholders to vote on Board, auditor, and expanded equity plan after a transformative year.LAC
Proxy filing1 Apr 2026 - Key votes include board size, director elections, auditor appointment, and equity plan approval.LAC
Proxy filing1 Apr 2026 - Up to $1B in securities registered to fund lithium project development and corporate needs.LAC
Registration filing1 Apr 2026 - $2.26B DOE loan, $625M GM JV, and $250M Orion investment drive Thacker Pass progress.LAC
Q3 202419 Mar 2026 - Thacker Pass fully funded for 2H24 construction start; cash up, net loss in H1 2024.LAC
Q2 202419 Mar 2026 - Construction advances with strong financing and cash, targeting late 2027 completion.LAC
Q2 202519 Mar 2026 - Fully funded for Thacker Pass Phase 1, with $446.9M cash and major construction milestones achieved.LAC
Q1 202519 Mar 2026 - Thacker Pass construction accelerates with major funding and higher net loss in Q3 2025.LAC
Q3 202519 Mar 2026 - Thacker Pass is set to become the largest, lowest-cost U.S. lithium producer by 2028.LAC
Corporate presentation19 Mar 2026