16 Mar, 2026Executive summary
Transitioned into gold production with first gold pour on 1 July 2025 and produced 16,322oz in the half-year ended 31 December 2025.
Open pit mining ramped up, Andy Well underground mine development commenced ahead of schedule, and preparations for Turnberry underground mine advanced.
No lost time injuries (LTIFR 0.0), TRIFR at 9.5, and no significant environmental incidents reported.
Financial highlights
Revenue of $65.2M from sale of 10,726oz gold for the half-year ended 31 December 2025.
Maiden Net Profit After Tax of $31.0M, compared to a net loss of $2.4M in the prior corresponding period.
EBITDA of $40.6M, up from $(1.0)M in the prior period.
Operating cash flow of $22.6M, compared to an outflow of $2.5M in the prior period.
Cash at bank of $37.3M as of 31 December 2025, down from $55.6M at 30 June 2025, reflecting $41.9M investment in asset construction and mine development.
Outlook and guidance
Growth activities resumed with extensional and exploration drilling yielding positive results and new target areas.
Company remains unhedged, retaining full leverage to gold price.
Latest events from Meeka Metals
- Transition to underground mining and exploration drive improved grades, production, and growth.MEK
Noosa Mining Conference 2026 - Transition to higher-grade underground ore is set to drive improved production and cash flow.MEK
Q4 2026 TU - Strong cash flow and plant upgrades position for higher gold output despite recent production dip.MEK
Q3 2026 TU - Murchison Gold Project fully funded and approved, targeting first production in mid-2025.MEK
H2 2024 - First gold production achieved, strong capital raising, and major ramp-up in mine development.MEK
H2 2025 - Production ramp-up is on track, with strong cash flow and significant growth potential.MEK
Corporate presentation - Gold output and cash flow surged, with strong exploration and plant upgrades underway.MEK
Q2 2026 TU - Gold output and cash reserves surpassed expectations, with costs below plan and growth capital deployed.MEK
Q1 2026 TU - Production ramping up with strong cash flow, robust growth, and first gold in July 2025.MEK
Noosa Mining Investor Conference