Meeka Metals (MEK) Q1 2027 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2027 TU earnings summary
28 Oct, 2026Executive summary
Produced 7,237oz of gold in the Sep-26 quarter, up from 6,424oz in Jun-26, as underground output ramped up and the processing plant reached its 600ktpa annualised target.
Shifted focus from open-pit mining to higher-grade underground operations; the Fairway decline at Turnberry is under development, with first ore expected in Jan-27.
Cash closed at $51.2M after a placement and $8.5M net mine cash flow; operations remain unhedged and have no debt other than mining equipment finance.
Financial highlights
Gold sales of 7,279oz generated $44.1M revenue at an average realised price of $6,063/oz.
All-in sustaining cost (AISC) was $4,147/oz; cash operating cost was $3,545/oz, including a favorable ore inventory adjustment of $357/oz.
Mine operating cash flow was $13.5M and net mine cash flow was $8.5M after $4.9M growth capital; depreciation and amortisation was $9.5M.
Appendix 5B reported $1.548M net cash from operating activities and $17.411M net investing cash outflow; financing generated $29.085M net cash.
Outlook and guidance
First ore from the Fairway decline is expected in Jan-27, adding a second high-grade underground ore source and reducing reliance on a single mining area.
Stage 1 of the two-stage tailings storage facility is expected to be commissioned in the Dec-26 quarter; the facility is designed for 10 years of capacity at 600ktpa.
The Steinert multi-sensor ore sorter was installed in early Oct-26, with commissioning commencing mid-October.
Underground drilling from Fairway platforms is planned to test mineralisation below the current Ore Reserve and support potential resource-to-reserve conversion and mine-life extension.
Latest events from Meeka Metals
- Production rose to 7,237oz as the operation shifted toward underground growth.MEK
Trading update - Underground mining ramp-up and Mt Holland acquisition drive growth, profitability, and resource expansion.MEK
Mining Forum Americas 2026 - First full year of gold production delivered $160.8M revenue and $51.3M net profit.MEK
H2 2026 - Transition to underground mining and exploration drive improved grades, production, and growth.MEK
Noosa Mining Conference 2026 - Transition to higher-grade underground ore is set to drive improved production and cash flow.MEK
Q4 2026 TU - Strong cash flow and plant upgrades position for higher gold output despite recent production dip.MEK
Q3 2026 TU - Murchison Gold Project fully funded and approved, targeting first production in mid-2025.MEK
H2 2024 - First gold production achieved, strong capital raising, and major ramp-up in mine development.MEK
H2 2025 - Delivered $31M net profit and strong cash flow following first gold production at Murchison.MEK
H1 2026