15 May, 2026Project commitment and overview
Approved construction of a 77 MW, 221 GWh per annum wind farm near Dargaville, with first generation expected by mid-2026 and full output by late 2026.
Forecast capital expenditure of $287 million, contributing to over $1 billion in new renewables investment for FY24 and FY25.
Multi-contract delivery approach adopted, leveraging experience from previous wind farm projects completed on time and under budget.
Grid location and wind profile enhance portfolio diversity and are expected to deliver higher generation-weighted average prices.
Technical and locational features
The wind farm will feature 12 Vestas V162 6.4MW turbines, the largest and tallest in New Zealand, with a tip height of 206m.
Underground 33kV lines will connect turbines to a 66kV onsite substation, with a 14km transmission line to Northpower's substation.
Proximity to Auckland and low correlation with the national wind fleet support higher average prices and partially offset higher capital costs.
Financial and operational metrics
Capital cost for Kaiwaikawe is $287 million, with total operating costs of $17.8/MWh and expected EBITDAF impact of $29 million in the first full year.
Net capacity factor is 33%, with a P50 yield of 221 GWh per annum over 30 years.
Final stages of negotiating offtake arrangements with Genesis.
Latest events from Mercury NZ
- Q4 trading margin surged 33% year-over-year, fueled by higher renewable generation and project milestones.MCY
Q4 2026 TU21 Jul 2026 - Lower profits, major renewable investment, and strong dividend growth highlighted at AGM.MCY
AGM 20258 Jul 2026 - Aims for NZD 1.15–1.25bn EBITDA by 2030, driven by renewables, digital, and scale.MCY
Investor Day 20258 Jul 2026 - EBITDAF down, net loss reported, but renewables investment and dividend growth continue.MCY
H1 20258 Jul 2026 - Record $877m EBITDAF, strong renewables, but FY25 outlook dampened by dry hydro and gas costs.MCY
H2 202416 Jun 2026 - EBITDAF dropped 10% to $786M, but renewables and growth drive a strong FY26 outlook.MCY
H2 202516 Jun 2026 - EBITDAF up 28% to $537m, net profit $20m, and renewables projects progressing strongly.MCY
H1 202616 Jun 2026 - Renewable growth, customer focus, and disciplined expansion drive long-term value.MCY
Corporate presentation15 Jun 2026 - Disciplined growth in renewables, cost efficiency, and innovation drive long-term value creation.MCY
Investor presentation15 May 2026