Minerals 260 (MI6) H2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2026 earnings summary
30 Sep, 2026Executive summary
Achieved a transformational year with the Bullabulling Gold Project, including a 170% increase in contained gold ounces since acquisition and a new Mineral Resource Estimate of 190Mt at 1.0g/t Au for 6.2Moz as of July 2026.
Completed a Pre-Feasibility Study (PFS) outlining a 19-year mine life, 2.3Moz total gold production, post-tax NPV5 of $2.3B, IRR of 43%, and a two-year capital payback.
Secured $420M in strategic funding from Franco-Nevada via royalty and equity transactions, plus a $250M equity placement, significantly strengthening the balance sheet.
Ended FY26 with $211.3M in cash and short-term deposits, supporting ongoing project development and the DFS.
Financial highlights
Net profit after tax of $83.5M for FY26, compared to a net loss of $11.5M in FY25, primarily due to $170M royalty income.
Exploration and evaluation expenditure rose to $57.4M (FY25: $7.2M), reflecting increased drilling and project development.
Corporate and admin expenses increased to $6.6M (FY25: $4.0M), mainly from higher personnel and transaction costs.
Cash and short-term deposits at 30 June 2026 totaled $211.3M (FY25: $54.4M).
Market capitalisation grew from ~$258M to ~$1.66B, with share price up 508% year-over-year.
Outlook and guidance
Definitive Feasibility Study (DFS) underway, targeting completion in Q1 CY27 and a final investment decision soon after.
First gold production targeted for Q4 CY28, subject to DFS, approvals, and financing.
Ongoing expansion of project area and resource base, with further drilling and exploration planned.
Latest events from Minerals 260
- Resource reaches 6.2Moz, major funding secured, and first production targeted for Q4 2028.MI6
Mining Forum Americas 2026 - Bullabulling advances toward late 2028 production, backed by strong funding and resource growth.MI6
Investor update - Project advances toward construction with major resource growth and strong financial backing.MI6
Resources Rising Stars Gold Coast Conference - Resource tripled to 6.2Moz, robust PFS, and major funding set stage for late 2028 output.MI6
Diggers & Dealers Mining Forum 2026 - Bullabulling Gold Project advances toward production with 6.2Moz resource, strong funding, and robust economics.MI6
Investor presentation - Bullabulling's PFS confirms A$2.3B NPV5, 43% IRR, and 6.2Moz resource, with first gold in Q4 CY2028.MI6
Q4 2026 TU - Resource and reserve growth, strong funding, and construction advancing toward 2028 output.MI6
Noosa Mining Conference 2026 - Major funding, resource growth, and fast-tracked development drive strong future prospects.MI6
Status update - Systematic project advancement and disciplined growth in mineral exploration were emphasized.MI6
AGM 2024