Minerals 260 (MI6) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
2 Aug, 2026Project overview and strategy
Bullabulling Gold Project resource increased from 2.3Moz to 6.2Moz in 15 months, making it one of Australia’s largest undeveloped gold resources and reserves not owned by a producer.
Maiden Ore Reserve of 2.5Moz underpins a 19-year mine life, with 85% of Indicated Resources converted to Probable Reserves.
Stage 1 PFS outlines a 5Mtpa operation, with infrastructure designed for potential expansion to 7.5Mtpa and production growth to 200kozpa.
Early construction activities, including village and water infrastructure, commenced in May 2026.
DFS and FID targeted for Q1 CY2027, with first gold production expected in Q4 CY2028.
Financials and funding
Post-tax NPV5 of A$2.3B, IRR of 43%, and a two-year payback period based on Stage 1 PFS.
Average annual EBITDA of A$510M and free cash flow of A$330M over a 19-year operating life.
A$560M construction capital plus A$180M pre-FID capital and A$115M pre-production operations.
Franco-Nevada committed A$220M (A$170M royalty, A$50M equity), marking its largest Australian investment.
Debt funding process advancing with multiple banks engaged and indicative term sheets received.
Resource and exploration
July 2026 Mineral Resource Estimate: 190Mt @ 1.0g/t Au for 6.2Moz (140Mt Indicated, 51Mt Inferred).
Ore Reserve: 90Mt @ 0.86g/t Au for 2.5Moz, based on December 2025 MRE.
Mineralisation remains open along strike and at depth, with ongoing drilling targeting extensions and new anomalies.
1,160km² of largely contiguous tenure supports further resource growth.
Latest events from Minerals 260
- Resource tripled to 6.2Moz, robust PFS, and major funding set stage for late 2028 output.MI6
Diggers & Dealers Mining Forum 2026 - Bullabulling's PFS confirms A$2.3B NPV5, 43% IRR, and 6.2Moz resource, with first gold in Q4 CY2028.MI6
Q4 2026 TU - Resource and reserve growth, strong funding, and construction advancing toward 2028 output.MI6
Noosa Mining Conference 2026 - Major funding, resource growth, and fast-tracked development drive strong future prospects.MI6
Status update - Systematic project advancement and disciplined growth in mineral exploration were emphasized.MI6
AGM 2024 - AGM focused on Bullabulling Gold Project growth, leadership updates, and 2028 production target.MI6
AGM 2025 - $220 million Franco-Nevada funding accelerates Bullabulling Gold Project toward 2028 production.MI6
Q3 2026 TU - Bullabulling acquisition completed, $220m raised, and FY25 ends with $54.3m cash on hand.MI6
H2 2025 - A$220M Franco-Nevada funding accelerates project toward 2028 production in WA.MI6
35th BMO Global Metals, Mining & Critical Minerals Conference