Minerals 260 (MI6) Q4 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2026 TU earnings summary
29 Jul, 2026Executive summary
Pre-Feasibility Study (PFS) completed, confirming Bullabulling as a high-margin, large-scale, long-life gold project with a post-tax NPV5 of A$2.3 billion and IRR of 43%.
Maiden Ore Reserve declared at 90Mt @ 0.86g/t Au for 2.5Moz, based on the December 2025 Mineral Resource Estimate (MRE) of 4.5Moz.
Updated MRE increased 38% to 190Mt @ 1.0g/t Au for 6.2Moz, with 4.4Moz classified as Indicated.
Early construction and development activities commenced, including village and water infrastructure, and grade control drilling.
Project area expanded to 1,160km² after acquiring additional tenure from Geko Explore.
Financial highlights
Strong financial position with approximately A$211 million in cash and deposits at 30 June 2026.
Net cash outflows from operating activities of A$28.7 million for the quarter, mainly due to increased exploration and PFS activity.
Cash outflows from investing activities totaled A$60.0 million, including tenement acquisitions and village construction.
Net cash outflows from financing activities were A$0.2 million.
Outlook and guidance
Definitive Feasibility Study (DFS) targeted for completion in Q1 CY2027, with Final Investment Decision (FID) and full-scale construction to follow.
First gold production expected in Q4 CY2028.
Debt funding process underway, with multiple indicative term sheets received and finalisation of debt terms planned to support FID.
Latest events from Minerals 260
- Resource tripled to 6.2Moz, robust PFS, and major funding set stage for late 2028 output.MI6
Diggers & Dealers Mining Forum 2026 - Bullabulling Gold Project advances toward production with 6.2Moz resource, strong funding, and robust economics.MI6
Investor presentation - Resource and reserve growth, strong funding, and construction advancing toward 2028 output.MI6
Noosa Mining Conference 2026 - Major funding, resource growth, and fast-tracked development drive strong future prospects.MI6
Status update - Systematic project advancement and disciplined growth in mineral exploration were emphasized.MI6
AGM 2024 - AGM focused on Bullabulling Gold Project growth, leadership updates, and 2028 production target.MI6
AGM 2025 - $220 million Franco-Nevada funding accelerates Bullabulling Gold Project toward 2028 production.MI6
Q3 2026 TU - Bullabulling acquisition completed, $220m raised, and FY25 ends with $54.3m cash on hand.MI6
H2 2025 - A$220M Franco-Nevada funding accelerates project toward 2028 production in WA.MI6
35th BMO Global Metals, Mining & Critical Minerals Conference