NextDecade (NEXT) Q2 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2025 earnings summary
10 Oct, 2025Executive summary
Executed a fixed price turnkey EPC agreement for Train 5 of the Rio Grande LNG Facility between Rio Grande LNG Train 5, LLC and Bechtel Energy Inc., dated June 12, 2025.
The agreement covers engineering, procurement, construction, pre-commissioning, commissioning, start-up, and testing of Train 5 and associated facilities.
The contract price is $4,319,981,000, subject to adjustment only by Change Order as provided in the agreement.
Commercialization of Train 4 completed with 20-year SPAs signed with Aramco and TotalEnergies; JERA signed as first long-term offtake for Train 5.
EPC contracts for Trains 4 and 5 finalized with Bechtel, with pricing valid through September 15, 2025.
Scope of work
Contractor is responsible for all engineering, procurement, construction, pre-commissioning, commissioning, start-up, and testing of Train 5, including all equipment, construction equipment, spare parts, labor, and training of Owner's personnel.
Contractor must integrate Owner's personnel into pre-commissioning, commissioning, testing, and start-up efforts.
The work includes all incidental work required to complete Train 5 in accordance with good engineering and construction practices, applicable law, and codes.
Key contractual terms
The contract price is separated into Aggregate Equipment Price and Aggregate Labor and Skills Price for tax purposes.
Interim payments are based on percent completion (Earned Value) and completion of payment milestones.
Change Orders are the exclusive mechanism for adjusting contract price, key dates, or scope.
Owner may issue Limited Notices to Proceed (LNTP) before full Notice to Proceed (NTP); NTP is subject to specific conditions precedent, including financing and permits.
Delay Liquidated Damages and Performance Liquidated Damages are specified, with aggregate caps on contractor liability.
Latest events from NextDecade
- FIDs for trains 4 and 5, $6.7B financing, and new SPAs drive strong LNG growth outlook.NEXT
Q4 20252 Mar 2026 - Proxy covers director elections, equity plan amendment, say-on-pay, and auditor ratification.NEXT
Proxy Filing2 Dec 2025 - $800M loan and $6.7B financing secured for LNG expansion, with strong covenants and SOFR rates.NEXT
Q3 202525 Nov 2025 - Train 5 FID secures 30 MTPA, 75% contracted, $6.7B funded, and major expansion potential.NEXT
Status Update22 Oct 2025 - LNG facility construction progresses on schedule, but regulatory and liquidity risks persist.NEXT
Q3 20244 Jul 2025 - Phase 1 construction and Train 4 progress continue despite regulatory and liquidity risks.NEXT
Q2 20244 Jul 2025 - Phase 1 is fully funded and on track, with expansion and regulatory progress advancing.NEXT
Q4 20244 Jul 2025 - LNG facility construction and expansion progress with strong contracts, financing, and demand.NEXT
Q1 20254 Jul 2025