NextDecade (NEXT) Q3 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2025 earnings summary
10 Jul, 2026Executive summary
Achieved positive Final Investment Decisions (FIDs) and financing for Rio Grande LNG Trains 4 and 5, each with $6.7 billion in project costs and expected 6 MTPA capacity per train, with both trains fully funded and construction underway.
Trains 1-3 are progressing ahead of schedule and on budget, with first LNG expected in 2027.
The Rio Grande LNG Facility is positioned to become one of the world’s largest LNG export sites, with up to 10 trains and a potential capacity of ~60 MTPA, projected to supply 5% of global LNG liquefaction capacity in the early 2030s.
Approximately 85% of Trains 1-5 capacity is contracted to 14 creditworthy counterparties through long-term SPAs, including agreements with EQT and ConocoPhillips for Train 5.
The company is advancing permitting for Trains 6-8 and exploring carbon capture and storage (CCS) projects, with pre-filing for Train 6 with FERC expected in 2025.
Financial highlights
Closed $6.7 billion project financings each for Train 4 and Train 5, including joint venture equity, company equity, and senior secured non-recourse bank credit facilities.
Phase 1 (Trains 1-3) fully funded with $18 billion in total sources, including $9.2 billion term loan and $6.2 billion equity.
Additional funding secured through delayed draw term loans, private placement notes, and an exchangeable loan of $100 million convertible into common stock at $9.50 per share, with interest rates ranging from 6.56% to 13.5%.
Projected steady state annual Rio Grande LNG Project-Level Adjusted EBITDA of $3.7 billion and distributable cash flow of $2.1 billion.
Attractive all-in cost of capital for Train 4 and 5 equity funding at ~9%.
Outlook and guidance
First LNG from Trains 1-3 expected in 2027; Trains 4 and 5 to follow, with full five-train operations by early 2030s.
Expansion trains (6-8) could increase project-level distributable cash flow by ~85%, with each train potentially generating over $0.6 billion annually.
Focused on safely completing and operating the first five trains, with plans to double LNG capacity by developing Trains 6-8.
Long-term LNG demand growth expected to remain robust, supporting further commercialization.
Latest events from NextDecade
- Trains 4 and 5 near FIDs as construction, contracts, and financing advance at Rio Grande LNG.NEXT
Q2 202510 Jul 2026 - Train 5 FID adds 6 MTPA, 75% contracted, fully funded, and targets completion by early 2031.NEXT
Status Update9 Jul 2026 - Diana Sands is confirmed as an independent director, correcting a prior omission.NEXT
Proxy filing19 May 2026 - Construction is ahead of schedule, major LNG sales secured, and expansion is progressing.NEXT
Q1 20261 May 2026 - Proxy seeks approval for director elections, equity plan amendment, pay, and auditor ratification.NEXT
Proxy filing29 Apr 2026 - FIDs for trains 4 and 5, $6.7B financing, and new SPAs drive strong LNG growth outlook.NEXT
Q4 20252 Mar 2026 - Proxy covers director elections, equity plan amendment, say-on-pay, and auditor ratification.NEXT
Proxy Filing2 Dec 2025 - LNG facility construction progresses on schedule, but regulatory and liquidity risks persist.NEXT
Q3 20244 Jul 2025 - Phase 1 construction and Train 4 progress continue despite regulatory and liquidity risks.NEXT
Q2 20244 Jul 2025