Nouveau Monde Graphite (NMG) 34th Annual BMO Global Metals, Mining & Critical Minerals Conference summary
Event summary combining transcript, slides, and related documents.
34th Annual BMO Global Metals, Mining & Critical Minerals Conference summary
16 Dec, 2025Project overview and strategy
Transitioned from grassroots exploration to a construction-ready, vertically integrated graphite project over 14 years.
Focuses on supplying engineered graphite materials for battery cell makers in North America and Europe.
Three-phase development: Matawinie Mine (100,000 tpa), Bécancourt Battery Material Plant, and a future 500,000 tpa project.
Phase one plant operational since 2018 for customer qualification and process optimization.
Updated feasibility study for phase two to be published before end of Q1.
Market dynamics and customer commitments
Graphite is essential for all battery chemistries, contributing significantly to battery carbon footprint.
90% of revenue expected from anode material, with the remainder from flake concentrate sales.
Secured seven-year take-or-pay agreements with Panasonic Energy and GM for 18,000 tpa each.
Customers aim to localize supply chains and reduce reliance on China, driven by U.S. plant expansions.
Record EV and ESS sales globally, with graphite demand rising for both sectors.
Financing, partnerships, and execution
Over $100 million in cash, fully financed to reach FID and project financing for phase two.
Major investors include Investissement Québec, Canada Growth Fund, Panasonic, GM, Mitsui, and Pallinghurst.
All stakeholders have submitted letters of interest; project financing expected to close within two quarters after feasibility study.
Construction activities started at Matawinie; Bécancourt site prepared and ready for build-out.
Targeting first production for customers in 2028, with phase three build readiness by then.
Latest events from Nouveau Monde Graphite
- Phased graphite projects target EV supply chains, with US$350M shelf for flexible capital raising.NMG
Registration Filing8 Dec 2025 - US$350M shelf offering targets graphite supply for EVs, with high risk and no current revenues.NMG
Registration Filing29 Nov 2025 - US$350M shelf registration to fund graphite and battery material projects for EV market.NMG
Registration Filing25 Nov 2025 - Q2 net loss widened to $21M; major projects advance but require substantial new funding.NMG
Q2 202527 Aug 2025 - Net loss widened to $51.4M as major financings offset ongoing cash burn and project costs.NMG
Q3 202413 Jun 2025 - Net loss widened to $43.3M as equity raises offset higher project and acquisition costs.NMG
Q2 202413 Jun 2025 - Q1 2025 net loss narrowed, project financing advanced, and cash reserves remain strong.NMG
Q1 202511 Jun 2025 - Advanced projects, secured $180M+ in equity, but faces funding risks before production.NMG
Q4 20245 Jun 2025