Nouveau Monde Graphite (NMG) Small Cap Growth Hybrid Investor Conference summary
Event summary combining transcript, slides, and related documents.
Small Cap Growth Hybrid Investor Conference summary
8 Oct, 2026Integrated development plan
Building a fully integrated Quebec graphite-to-anode-material business, with a 106,000-tonne-per-year mine under construction since May and ~25% of its production intended for processing in Bécancour.
Mine construction was described as on track and on budget; commissioning is targeted for end-2028, followed by a six-month ramp-up.
Mine CapEx was updated from CAD 421 million to CAD 474 million, including CAD 53 million added for potential cost escalation.
Bécancour is targeting an FID within the next few months; acquiring an adjacent brownfield facility is expected to reduce CapEx and accelerate development.
Uatnan could reach 500,000 tonnes per year over 24 years, versus its original 50,000-tonne, 240-year design; it is intended as a later expansion following Matawinie.
Customers and market positioning
Three key offtake arrangements involve the Canadian government, Panasonic Energy and Traxys, spanning specialty graphite, battery anode material and refractory-brick markets.
Panasonic Energy is the targeted customer for anode material; the speaker cited anode demand as a key rationale for mine scale and described Panasonic as seeking a reliable second source beyond China.
A Canadian government buyers’ club is intended to support bankability and market sales to G7 customers, with profit sharing; the government named the project a major project of national interest last November.
Eni invested CAD 70 million at $1.84 per share in May and signed an LOI; potential supply to its Italian joint ventures is being explored.
Graphite demand is exposed to China’s dominance in uncoated spherical graphite; North American production scarcity and customer interest in supply diversification were presented as strategic advantages.
Financial outlook and expansion opportunities
NI 43-101 mine guidance cited CAD 139 million in revenue, CAD 44 million in OpEx and CAD 95 million in EBITDA; the EBITDA figure was presented as a 2029 run rate.
The after-tax unlevered IRR was 15.8%; sensitivity to graphite prices near $1,500 was said to add ~300 bps, while offtake contracts have price floors but no price ceiling.
Cash was cited at CAD 461 million, with CAD 12.5 million in funded debt; the speaker described the balance sheet as favorable for construction.
Potential value growth includes tailings-derived sulfuric acid and advanced graphite materials such as stealth products; these opportunities remain under exploration.
A midterm scenario combining the mine with Bécancour, a possible European sister plant and tailings opportunities could reach $250 million in EBITDA, according to the speaker.
Latest events from Nouveau Monde Graphite
- Launched Matawinie Mine construction after major financing, advancing integrated graphite operations.NMG
Q2 2026 - Advancing large-scale, integrated graphite projects with strong ESG and market positioning.NMG
Corporate presentation - Set to lead Western graphite supply with integrated operations, ESG focus, and strong market demand.NMG
Corporate presentation - Phased graphite projects target EV supply chains, with US$350M shelf for flexible capital raising.NMG
Registration Filing - US$350M shelf offering targets graphite supply for EVs, with high risk and no current revenues.NMG
Registration Filing - US$350M shelf registration to fund graphite and battery material projects for EV market.NMG
Registration Filing - Q2 net loss widened to $21M; major projects advance but require substantial new funding.NMG
Q2 2025 - Advancing a low-carbon, fully financed graphite supply chain for North American battery markets.NMG
34th Annual BMO Global Metals, Mining & Critical Minerals Conference - Advanced financing, major offtakes, and strong ESG progress position for Phase-2 launch.NMG
Q4 2024