  • Transitioned from development to execution with the Financial Investment Decision (FID) and construction launch of the Matawinie Mine Phase 2, supported by significant equity and debt financing.

  • Established a strategic supply and marketing framework with the Government of Canada, including long-term take-or-pay agreements for 30ktpy of flake graphite.

  • Advanced commercial discussions for additional offtake agreements, notably with Eni S.p.A. for up to 15ktpy graphite concentrate.

Financial highlights

  • Completed a private placement and subscription receipts for aggregate gross proceeds of C$427 million (US$310M) in Q2 2026.

  • Period-end cash position of C$461 million as of June 30, 2026.

  • Incurred C$33 million in project expenditures and committed C$167 million for Matawinie Mine construction by quarter-end.

Outlook and guidance

  • Focused on advancing civil works at Matawinie, securing FID for the 13ktpy Bécancour Battery Material Plant in H2 2026, and expanding business development.

  • Plans to pursue additional battery material plants and diversify product offerings to meet growing customer demand.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more