Orvana Minerals (ORV) Corporate presentation summary
Event summary combining transcript, slides, and related documents.
Corporate presentation summary
15 Apr, 2026Strategy and operations overview
Focus on three 100%-owned assets: Orovalle (Spain), Don Mario (Bolivia), and Taguas (Argentina), each at different stages of production and exploration.
Orovalle has delivered stable production since 2011, with ongoing brownfield and greenfield exploration to expand resources.
Don Mario is resuming production in 2026, with a ramp-up of oxide stockpile processing and plant expansion, targeting stable cash flow.
Taguas is advancing with its first deep drilling campaign, targeting copper-gold porphyry potential, with results expected to inform long-term strategy.
Financial and production performance
FY2025 revenue was $98.9M, with a net loss of $12.3M and EBITDA of $21.4M; Q1 FY2026 revenue was $32.0M with a net loss of $7.2M.
Orovalle produced 29.3k oz gold, 115.5k oz silver, and 3.6M lbs copper in FY2025.
FY2027 production targets: 65k oz gold and 19M lbs copper across all operations.
As of December 31, 2025, unrestricted cash was $32.2M, with no debt and a market capitalization of $230M CAD.
Asset and resource highlights
Orovalle (Spain): Proven and probable reserves of 2.53Mt at 2.61 g/t Au, 0.25% Cu, and 4.10 g/t Ag; measured and indicated resources of 7.53Mt at 3.36 g/t Au, 0.36% Cu, and 6.72 g/t Ag.
Don Mario (Bolivia): Proven reserves of 2.03Mt at 1.85 g/t Au, 1.89% Cu, and 49.3 g/t Ag; measured resources of 2.18Mt at 1.84 g/t Au, 1.89% Cu, and 49.3 g/t Ag.
Taguas (Argentina): Indicated oxide resources of 39.5Mt at 0.37 g/t Au and 11.1 g/t Ag; inferred sulfide resources of 80.4Mt at 0.28 g/t Au, 7.5 g/t Ag, and 0.17% Cu.
Latest events from Orvana Minerals
- Bolivian ramp-up and Argentina exploration set to transform gold and copper output this year.ORV
Mining Forum Europe 202613 Apr 2026 - Production rebounded in Spain, Bolivian restart advanced, and FY2026 guidance reaffirmed.ORV
Q1 20266 Mar 2026 - Revenue rose in FY2025 as Spain remained stable and Bolivia's Don Mario expansion advanced.ORV
Q4 20255 Dec 2025 - Q3 results improved on higher production and prices; Don Mario financing advances for expansion.ORV
Q3 202420 Oct 2025 - Production fell 22% in FY2024, but Bolivia project funding and construction advanced.ORV
Q4 202420 Oct 2025 - Q1 FY2025 featured Don Mario expansion progress, lower Orovalle output, and steady financials.ORV
Q1 202520 Oct 2025 - Q2 FY2025 saw Don Mario expansion progress and Orovalle production decline, with revenue up.ORV
Q2 202520 Oct 2025 - Don Mario expansion on track; Orovalle revises gold guidance down, copper up for FY2025.ORV
Q3 202520 Oct 2025