Osisko Gold Group (OGG) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
17 Jul, 2026Strategic vision and project overview
Advancing the Cariboo Gold Project in British Columbia, a fully permitted, shovel-ready underground gold mine with a 10-year life and significant scalability potential.
Cariboo Gold Project features 2.07 Moz probable reserves, 1.61 Moz measured & indicated resources, and 1.86 Moz inferred resources, with robust economics and expansion potential.
The Tintic Project in Utah, USA, offers additional upside with high-grade gold and silver resources and ongoing exploration.
Led by an experienced management team with a track record of successful mine development and stakeholder engagement.
Focus on responsible mining, strong Indigenous and community relations, and sustainable practices.
Financial strength and project financing
Over US $1.1B raised since securing project financing, including $435M equity and $360M debt.
Convertible senior notes of US $300M with a 4.125% coupon, 25% conversion premium, and capped call to mitigate dilution.
Project debt financing includes an initial US $100M draw and a subsequent US $350M draw, with flexible terms and interest rates.
Strong cash position ($594M) and market capitalization of C$1.15B as of July 2026.
Flexible capital structure and broad institutional investor base, including significant support from major asset managers.
Cariboo Gold Project technical and economic highlights
Feasibility study outlines 190 koz/year LOM average gold production (202 koz/year first 5 years), US $1,157/oz AISC, and 92.6% recovery.
Initial capex of $881M (US $652M), after-tax NPV5% of $943M at US $2,400/oz gold, and IRR of 22.1%.
Positioned in the lower half of the global gold cost curve, competitive with leading Canadian underground mines.
Mine design features bulk tonnage long-hole mining, ore sorting, and a single processing facility with gravity and flotation circuits.
Significant exploration and resource conversion potential, with mineralization open at depth and along strike.
Latest events from Osisko Gold Group
- Cariboo construction is underway, with first gold targeted for Q1 2029 and $907 million remaining cost estimate.OGG
Q3 2026 - Cariboo construction is underway, targeting first gold in Q1 2029.OGG
Investor presentation - Aggressive mine build and drilling aim to double gold output and resource base by 2029.OGG
Mining Forum Americas 2026 - Revenue surged and operating income turned positive as gold sales and project development accelerated.OGG
Q2 2026 - Cariboo Gold is on track for major growth, with robust funding, drilling, and top-tier mine ambitions.OGG
John Tumazos Very Independent Research 2026 Virtual Conference - Cariboo Gold Project advances toward production with strong financing, low costs, and growth potential.OGG
Investor presentation - US$300M convertible notes and capped call offer flexible, low-cost funding and dilution protection.OGG
Investor presentation - Cariboo Gold Project advances toward top-tier gold production with strong economics and growth potential.OGG
Investor presentation - $594.3M cash, Cariboo Gold Project resumed, $143.8M US raised, Tintic gold sales $2.2M.OGG
Q1 2026