Pacific Lime and Cement Limited (PLA) Q4 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2026 TU earnings summary
31 Jul, 2026Executive summary
Achieved major construction milestones at the Central Lime Project, including completion of 27.6km of roads and two river bridges, providing first-time access between the project site and Port Moresby.
Kiln foundations and wharf extension advanced, with 369 foundation piles delivered and plant fabrication progressing.
Workforce more than doubled to 391, with significant increase in local employment.
PNG Government, via KMHL, executed a US$16.3 million equity investment for a 13% stake in the Central Lime Project, with options for further participation.
IFC-supported feasibility and market assessment for the Central Cement Project advanced, targeting FID later in 2026.
Financial highlights
Cash holdings at 30 June 2026 were A$16.7 million.
A$24.5 million spent on exploration and development during the quarter, mainly for Central Lime Project construction.
Net cash used in operating activities for the quarter was A$3.03 million; net cash used in investing activities was A$26.56 million.
Proceeds from equity issues totaled A$0.77 million for the quarter.
Convertible note facility of US$10 million (A$14.94 million) fully drawn.
Outlook and guidance
Central Lime Project construction to continue across all workstreams, targeting first production in Q1 CY2027.
Two-lane road and bridge completion expected by 30 September 2026.
Central Cement Project to host IFC site visit, conclude feasibility update, and receive EPC bids by end of September 2026.
Orokolo Bay project to advance customer offtake and logistics, with readiness documentation to be finalized.
Mayur Renewables to progress regulatory engagement and benefit-sharing workstreams.
Latest events from Pacific Lime and Cement Limited
- Integrated lime and cement project in PNG targets regional supply gaps with strong government and IFC backing.PLA
Investor presentation31 Jul 2026 - Project funding, legal wins, and capital raises drive early revenue and asset growth.PLA
H2 20248 Apr 2026 - Achieved FID for Central Lime Project, first quicklime sales, and returned to profitability.PLA
H2 20258 Apr 2026 - Shareholders raised governance and diversity issues, with all resolutions voted online and results pending.PLA
AGM 202411 Jan 2026 - Equity raising secures funding for scalable lime and cement project with strong market demand.PLA
Corporate Presentation1 Jul 2025 - A$100.1 million raised, projects fully funded, and major construction milestones achieved.PLA
Q3 2025 TU22 Jun 2025 - US$50 million financing and legal wins position Mayur for growth in lime and carbon projects.PLA
Q1 2025 TU13 Jun 2025 - USD 50M investment secured for Central Lime Project, construction to start after funding closes.PLA
Q4 2024 TU13 Jun 2025 - Loss widens as Mayur secures major funding and advances key PNG resource projects.PLA
H1 20256 Jun 2025