Investor presentation
Logotype for PT Merdeka Copper Gold Tbk

PT Merdeka Copper Gold (MDKA) Investor presentation summary

Event summary combining transcript, slides, and related documents.

Logotype for PT Merdeka Copper Gold Tbk

Investor presentation summary

22 Jan, 2026

Portfolio overview and key assets

  • Controls significant assets in Indonesia with large resources in gold, copper, nickel, and cobalt.

  • Pani Gold Project under construction, targeting 500,000 oz annual gold production and multi-decade mine life.

  • Tujuh Bukit Copper Project is a development-ready, long-life underground mine with 8.5Mt copper and 27.9Moz gold resources.

  • Wetar Copper/Pyrite Mine is a mature operation with valuable pyrite stockpiles and 2024 guidance of 14,000–16,000 tonnes copper.

  • MBM assets include one of the world's largest nickel deposits and integrated battery materials processing facilities.

Financial and operational highlights

  • Pani Gold Project projects a post-tax NPV8 of $2.6b, 40% IRR, and $550m average annual EBITDA.

  • Cumulative LOM gold production at Pani expected to reach 4.7Moz with peak annual output of 500,000 oz.

  • TB Copper Project targets first quartile AISC of $1.0/lb net of gold credits, with estimated pre-production capex of $750m.

  • TB Gold Mine has produced over 1 million oz since 2017, with 2024 guidance of 100–120koz at $900–1,050/oz cash cost.

  • MBM's RKEF plants and nickel matte converter target 2024 production of up to 92,000 tonnes NPI and 55,000 tonnes high-grade nickel matte.

Development progress and strategy

  • Pani Gold Project construction ongoing, with first gold expected in 2025 and CIL processing by 2028.

  • TB Copper Project will extract only 24% of defined resource, using underground mining and panel caving.

  • MBM developing multiple HPAL plants with partners GEM and CATL, targeting 115ktpa nickel capacity by 2027.

  • AIM plant operational, producing acid and steam for HPAL, with all circuits to be fully operational by late 2024.

  • Dedicated haul roads and supporting infrastructure in place for SCM Mine and Pani Project.

Partial view of Summaries dataset, powered by Quartr API