PT Merdeka Copper Gold (MDKA) Q4 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2025 earnings summary
13 Apr, 2026Executive summary
Consolidated revenue for FY2025 was $1.89 billion, down 15% year-over-year, mainly due to lower HGNM and NPI contributions, partially offset by higher gold and nickel ore sales and prices.
EBITDA for FY2025 was $373 million, driven by improved profitability in NPI, nickel ore, and gold segments, and a 32% YoY increase in average gold selling price.
Net income for FY2025 was $16 million, with net profit margin at 0.9%.
Strategic projects, including the Pani Gold Project and nickel downstream facilities, advanced significantly, with the first gold sale from Pani and a maiden mineral resource at Gua Macan.
Diversified portfolio across gold, copper, and nickel segments underpins stable performance and cash flow.
Financial highlights
Revenue: $1.89 billion (down 15% YoY); EBITDA: $373 million (up 13% YoY); Net income: $16 million.
MBMA revenue: $1.43 billion (down 22% YoY); EBITDA: $219 million (up 34% YoY).
Gross profit margin improved to 11.4% from 7.9% YoY; EBITDA margin increased to 19.7%.
Nickel ore production grew 44% YoY, contributing to overall financial strength.
Finance costs rose with higher debt, reaching $117 million for the year.
Outlook and guidance
2026 gold production guidance: TB Gold 80,000–90,000 oz, Pani 100,000–115,000 oz; copper: 4,000–5,000 t.
Saprolite ore sales targeted at 8.0–10.0 million wmt, limonite at 20.0–25.0 million wmt.
NPI production guidance: 70,000–80,000 t; HGNM: 44,000–48,000 t; MHP: 27,000–30,000 t.
Cost guidance: gold AISC $1,300–$2,050/oz, copper AISC $4.00–$4.70/lb, NPI cash cost below $10,500/tNi.
Commissioning of the HPAL project’s first production line is targeted for mid-2026.
Latest events from PT Merdeka Copper Gold
- Revenue surged 152.6% and audit confirmed fair presentation, with key project progress.MDKA
Q1 202422 Jan 2026 - Strong revenue and EBITDA growth, but net loss widened; unqualified audit opinion issued.MDKA
Q3 202422 Jan 2026 - Major Indonesian mining group advances gold, copper, and nickel projects with strong ESG focus.MDKA
Investor presentation22 Jan 2026 - Advancing world-class gold, copper, and nickel projects with strong ESG and financial performance.MDKA
Investor presentation22 Jan 2026 - Revenue surged 110% YoY to $1.09B, with strong gold and nickel growth and net profit up 137%.MDKA
Q2 202422 Jan 2026 - Revenue rose 31% to $2.24B, net profit $10M, with strong nickel output and major projects.MDKA
Q4 202422 Jan 2026 - EBITDA rose 57% to $89 million as revenue fell 7% to $502.2 million in Q1 2025.MDKA
Q1 202522 Jan 2026 - EBITDA grew 18% despite a 22% revenue drop; audit found no impairment indicators.MDKA
Q2 202522 Jan 2026 - EBITDA up 33% and net profit up 173% YoY, with unqualified audit and strong project progress.MDKA
Q3 202522 Jan 2026