Rail Vikas Nigam (RVNL) Q4 07/08 earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Rail Vikas Nigam Limited

Q4 07/08 earnings summary

26 Oct, 2026

Executive summary

  • FY 2007-08 project expenditure reached Rs.1,618.73 crore; the Directors’ Report described project-execution turnover as up 30.94% YoY to the same amount. The audited P&L separately lists turnover of Rs.1,423.11 crore.

  • Profit before tax was Rs.39.34 crore, profit after tax Rs.28.43 crore and basic EPS Rs.0.21; the Board recommended a Rs.5 crore dividend.

  • Nine projects spanning about 231 km were completed during the year; reported cumulative completion reached about 36% of the 6,686 km in the 55-project portfolio.

Financial highlights

  • Audited P&L turnover was Rs.1,423.11 crore versus Rs.985.26 crore in FY 2006-07; project execution income was Rs.19.67 crore versus Rs.3.59 crore.

  • Gross profit rose to Rs.46.78 crore from Rs.18.20 crore; PBT increased to Rs.39.34 crore from Rs.15.25 crore.

  • PAT was Rs.28.43 crore versus Rs.11.27 crore; EPS was Rs.0.21 versus Rs.0.12.

  • Net worth increased to Rs.2,119.09 crore from Rs.1,676 crore; paid-up share capital rose to Rs.2,015.02 crore from Rs.1,150.02 crore.

  • Short-term deposit interest income was Rs.19.67 crore versus Rs.11.66 crore; direct tax paid was Rs.11.08 crore versus Rs.3.98 crore.

Outlook and guidance

  • FY 2008-09 MoU targets: 240 km gauge conversion, 260 km doubling, 80 km railway electrification and 5 km new line; estimated expenditure Rs.1,725 crore.

  • Longer-term project expenditure ambition was Rs.3,000 crore annually; the Chairman’s address also set Rs.2,000 crore as the current-year project-expenditure target.

  • Railway Board targeted commissioning 863 km of work in FY 2008-09, versus 221 km physically commissioned across new line, gauge conversion, doubling and electrification in FY 2007-08.

  • A second ADB loan was under processing; three newly assigned projects were expected to use that financing.

Partial view of Summaries dataset, powered by Quartr API
AI can get things wrong. Verify important information.
All investor relations material. One API.
Learn more

Latest events from Rail Vikas Nigam