FY13 turnover reached ₹2,116.85 crore, up 32% YoY; PAT rose to ₹135.55 crore, the first year above ₹100 crore.
Physical delivery included 237 km of doubling and 188 km of pure railway electrification; 423 km completed in total, plus 215 km of electrification within other projects.
Recommended dividend was a record ₹27 crore; expected FY13 MoU rating remained Excellent.
Financial highlights
Revenue from operations was ₹2,116.85 crore vs ₹1,597.92 crore YoY; total revenue was ₹2,204.96 crore vs ₹1,654.29 crore.
PBT rose to ₹167.46 crore from ₹119.33 crore; PAT increased to ₹135.55 crore from ₹98.38 crore.
EPS was ₹0.65 vs ₹0.47; reserves and surplus stood at ₹332.58 crore vs ₹226.77 crore.
Ministry of Railways project turnover grew to ₹1,898.47 crore from ₹1,365.59 crore; SPV and other deposit work turnover was ₹212.22 crore vs ₹215.76 crore.
Project-execution income rose to ₹89.56 crore from ₹67.48 crore, excluding DPE-guideline fund appropriations; dividend income increased ₹7.5 crore, with remaining profit growth attributed to bank and SPV interest.
Outlook and guidance
FY14 MoU targets: 250 km of doubling/third line and 200 km of railway electrification; turnover target ₹2,200 crore, with an aim to exceed it.
FY14 execution priorities include second-tranche ADB projects, newly transferred works, Kolkata Metro expansion and workshop projects.
Expected FY13 MoU rating was Excellent, after exceeding the physical targets of 230 km doubling and 180 km electrification.
Latest events from Rail Vikas Nigam
- H1 profit rose on broadly steady revenue; a JV loan guarantee and disputed receivables remain key watchpoints.RVNL
Q2 26/27 - Project execution and profit grew, but cost, capacity and asset-transfer risks persisted.RVNL
Q4 07/08 - Project execution accelerated, while audit flags exposed tax and asset-transfer uncertainties.RVNL
Q4 06/07 - 5% turnover growth, higher PAT, and a ~Rs 19,000 crore rail project pipeline.RVNL
Q4 08/09 - Higher earnings and project delivery, tempered by funding and land-acquisition risks.RVNL
Q4 09/10 - Turnover and profits rose as project delivery accelerated and a US$500 million ADB facility advanced.RVNL
Q4 11/12 - Lower turnover, higher profit, and 441 km delivered marked FY11.RVNL
Q4 10/11 - Record turnover and project delivery, alongside execution risks and qualified consolidated accounts.RVNL
Q4 14/15 - Record FY16 results and project delivery, with growth reliant on funding and execution conditions.RVNL
Q4 15/16