West Wits Mining (WWI) H2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2026 earnings summary
31 Aug, 2026Executive summary
Achieved first gold production at Qala Shallows in March 2026, producing 227oz by year-end, marking transition from developer to producer.
Secured ZAR1.115 billion (~A$97m) project finance package with Absa and Nedbank, fully funding ramp-up to steady-state production.
Expanded Witwatersrand Basin Project (WBP) Mineral Resource Estimate to 7.24Moz Au, a 2.2Moz increase year-over-year.
Divested non-core Mt Cecelia Project to focus on WBP.
Workforce grew to 431, with ongoing community and skills programs.
Financial highlights
Revenue from gold sales: $197,000 (first production year).
Net loss after tax: $9,977,000 (vs. $3,272,000 prior year), reflecting ramp-up costs and development expenses.
Cash at year-end: $32.0 million.
Total assets: $110.1 million; total liabilities: $31.8 million.
No dividends declared.
Outlook and guidance
Targeting steady-state production of ~70,000oz gold per annum by FY2028/29.
Project 200 Scoping Study completed, assessing pathway to 200,000oz per annum; further studies and resource upgrades planned.
Grid power connection expected early 2027 to reduce diesel reliance.
Latest events from West Wits Mining
- Gold production ramping to 70,000 oz/year with strong margins and major growth potential.WWI
Investor presentation - Major operational breakthrough, full project funding secured, and gold production ramping up.WWI
Q4 2026 TU - Fully funded gold project with 7.24Moz resource, robust economics, and major expansion plans.WWI
Investor presentation - First gold pour achieved, ramp-up underway, and funding secured for steady-state production.WWI
Q3 2026 TU - Fully funded, ramping up Qala Shallows for first gold in March 2026, with expanded WBP ownership.WWI
H1 2026 - Qala Shallows is production-ready with financing in progress, but going concern risks remain.WWI
H2 2024 - Secured major funding, advanced Qala Shallows, and posted a $3.68m FY25 loss with strong cash reserves.WWI
H2 2025 - First gold expected March 2026, with major expansion and strong ESG focus underway.WWI
RIU Explorers Conference 2026 - Fully funded gold project with 7.24Moz resource, strong economics, and first gold in March 2026.WWI
Investor presentation