West Wits Mining (WWI) Investor update summary
Event summary combining transcript, slides, and related documents.
Investor update summary
15 Oct, 2026Production ramp-up
Recovered gold forecast at 10,000–15,000 oz in 2027, 42,500 oz in 2028 and 70,000 oz in 2029; steady-state production is targeted for Q1 2029.
First primary, high-grade stoping is scheduled for February 2027; development ounces remain secondary to building access and infrastructure.
Ramp-up is non-linear, requiring six half-levels for sustainable steady-state production; capacity is ~840,000 tonnes of ore per year.
Development and infrastructure
Underground development reached 1,150m by end-September 2026: 513m of reef development and 637m of waste development; September advance was a record 200m, against a 600m/month target for 2027.
The 1 West Decline connected to the historic 2 Level area on 21 May 2026, opening access to unmined stopes; Level 4 access is expected to start opening in Q1 2027.
Surface infrastructure was 61% complete at end-September 2026, with critical works targeted for Q3 2027; the haulage road is complete and handed over.
2.5MW backup generators were scheduled for commissioning in October 2026; bulk power connection is planned for early 2027, following City Power technical adjudication.
Funding
Funding includes a R875M (~A$76M) senior debt facility, R150M (~A$13M) working-capital facility and R90M (~A$8M) cost-overrun debt facility; a R57M (~A$5M) cost-overrun equity facility is also available.
The second senior debt drawdown of R236M (~A$21M) was received after cost-to-complete and covenant testing; R575M (~A$50M) of senior debt had been drawn, with R300M (~A$26M) available.
The project is fully funded to steady-state production; management does not currently expect to draw the working-capital or cost-overrun facilities and said it does not intend to raise equity for Qala Shallows.
Latest events from West Wits Mining
- Faster development and secured funding advance Qala Shallows toward 70,000oz p.a. production.WWI
Q1 2027 TU - Gold production ramping to 70,000 oz/year with strong margins and major growth potential.WWI
Investor presentation - First gold poured, resource base expanded, and full project financing secured for ramp-up.WWI
H2 2026 - Major operational breakthrough, full project funding secured, and gold production ramping up.WWI
Q4 2026 TU - Fully funded gold project with 7.24Moz resource, robust economics, and major expansion plans.WWI
Investor presentation - First gold pour achieved, ramp-up underway, and funding secured for steady-state production.WWI
Q3 2026 TU - Fully funded, ramping up Qala Shallows for first gold in March 2026, with expanded WBP ownership.WWI
H1 2026 - Qala Shallows is production-ready with financing in progress, but going concern risks remain.WWI
H2 2024 - Secured major funding, advanced Qala Shallows, and posted a $3.68m FY25 loss with strong cash reserves.WWI
H2 2025