West Wits Mining (WWI) Q4 2026 TU earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for West Wits Mining Limited

Q4 2026 TU earnings summary

27 Jul, 2026

Executive summary

  • Achieved 1 West Decline breakthrough at Qala Shallows, unlocking access to higher-grade stoping areas and accelerating production ramp-up.

  • Underground development totaled 544m for the quarter, with 375m on-reef and 168m waste development.

  • Delivered 4.6kg (148oz) of gold in the quarter, with YTD production at 7.05kg (227oz).

  • Surface infrastructure 45% complete, including haulage road, warehouse, and pollution control dam.

  • Completed full project finance package and repaid Nebari bridge loan, securing long-term funding.

Financial highlights

  • Cash at 30 June 2026 was approximately A$32M.

  • Quarterly expenditure: $11.1M on Qala Shallows development and $2.8M on plant and equipment.

  • Net cash used in operating activities for the quarter: A$3.26M; investing activities: A$13.93M; financing activities: net inflow of A$9.26M.

  • Cash and cash equivalents at period end: A$32.1M.

Outlook and guidance

  • Project 200 Scoping Study expanded to assess multiple development and processing pathways, targeting up to 200,000oz per annum; results expected early August 2026.

  • Plans to implement exploration program for Bird Reef Central Uranium/Gold Project.

  • Operational focus for next quarter: advance development rates, ramp up production, and execute Scoping Study.