NHPC (NHPC) Q4 22/23 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 22/23 earnings summary
28 Oct, 2026Executive summary
Standalone PAT reached a record ₹3,833.79 crore in FY23, up 8.37% YoY; consolidated PAT was ₹4,234.74 crore, versus ₹3,774.33 crore.
Generation reached 24,907 MUs, the second-highest annual total, while plant availability hit a record 88.75%.
Growth plans span major hydro construction, Nepal projects, solar, pumped storage and pilot green hydrogen initiatives.
Financial highlights
Standalone total income was ₹10,150.90 crore, up from ₹9,335.40 crore; revenue from operations was ₹9,316.34 crore versus ₹8,309.22 crore.
Standalone expenses rose to ₹5,567.30 crore from ₹5,288.54 crore; finance costs fell to ₹476.16 crore from ₹531.75 crore.
Standalone total comprehensive income was ₹3,830.42 crore, versus ₹3,550.47 crore; consolidated total income was ₹11,284.90 crore and expenses ₹6,028.22 crore.
Adjusted energy sales, excluding prior-year sales, were ₹8,592.30 crore versus ₹7,891.89 crore; reported energy sales include ₹532.55 crore of prior-year sales.
Outlook and guidance
Targeted commissioning of 2,000 MW Subansiri Lower and 800 MW Parbati-II in FY24; both projects are in advanced construction and commissioning stages.
Nine hydro projects totaling 9,314 MW were under construction, including 5,680 MW on a standalone basis and 3,634 MW through subsidiaries/JVs.
Six projects totaling 4,112 MW were at clearance or approval stages; further hydro projects and investigation work extend the development pipeline.
Solar projects totaling 1,000 MW under EPC were expected to commission in phases in FY24 and FY25, subject to module availability and transmission infrastructure.
Planned pilot green hydrogen projects in Ladakh and Himachal Pradesh, alongside development of pumped storage projects across several states.
Latest events from NHPC
- H1 growth and hydro commissioning advanced amid higher costs and tariff uncertainty.NHPC
Q2 26/27 - Higher profit and availability, offset by project risks and audit qualifications.NHPC
Q4 01/02 - Higher earnings and collections, alongside ambitious hydro expansion and audit risks.NHPC
Q4 00/01 - Generation beat target, but state arrears and audit disputes clouded growth.NHPC
Q4 98/99 - Profit rose despite lower sales and generation shortfalls from weak river inflows.NHPC
Q4 99/00 - Record generation and earnings underpin a major hydro-renewables expansion.NHPC
Q4 21/22 - Lower hydro output pressured earnings as a >10,000 MW clean-energy pipeline advanced.NHPC
Q4 23/24 - Record availability and 380 MW added, offset by lower consolidated earnings and project risks.NHPC
Q4 17/18 - Higher FY17 profit and availability, offset by project delays and major shareholder payouts.NHPC
Q4 16/17