NHPC (NHPC) Q4 99/00 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 99/00 earnings summary
28 Oct, 2026Executive summary
FY1999-2000 sales turnover was Rs.12,163 million, down from Rs.13,094 million; net profit rose to Rs.4,012 million from Rs.3,053 million, supported by cost controls and staff redeployment.
Hydropower generation fell short of target on weak river inflows, especially in the Jhelum basin; average machine availability reached 91.05%.
Financial highlights
Sales were Rs.12,163 million vs Rs.13,094 million; sales net of advance against depreciation were Rs.10,757 million vs Rs.11,944 million.
Profit before depreciation, interest and financing charges rose to Rs.10,675 million from Rs.9,545 million; interest and finance charges were Rs.4,497 million vs Rs.4,787 million.
Profit after interest, financing charges and depreciation was Rs.3,980 million; after prior-period adjustments of Rs.32 million, reported profit was Rs.4,012 million vs Rs.3,053 million.
Proposed dividend remained Rs.150 million; reserves and surplus increased to Rs.16,906 million from Rs.12,721 million.
Outlook and guidance
Generation in FY2000-01 was expected to meet target, based on output through July 2000, which exceeded target to date.
Chamera-II, Kurichu and Kalpong were progressing ahead of schedule; projected completions were May 2004, September 2001 and June 2001, respectively.
Dhauliganga was targeted for completion by March 2005; Dul Hasti was expected to complete by December 2003 despite tunnel delays.
Teesta-V was sanctioned at Rs.21,980.4 million; Loktak Downstream works advanced, while security conditions were hampering execution.
Latest events from NHPC
- H1 growth and hydro commissioning advanced amid higher costs and tariff uncertainty.NHPC
Q2 26/27 - Higher profit and availability, offset by project risks and audit qualifications.NHPC
Q4 01/02 - Higher earnings and collections, alongside ambitious hydro expansion and audit risks.NHPC
Q4 00/01 - Generation beat target, but state arrears and audit disputes clouded growth.NHPC
Q4 98/99 - Record generation and earnings underpin a major hydro-renewables expansion.NHPC
Q4 21/22 - Lower hydro output pressured earnings as a >10,000 MW clean-energy pipeline advanced.NHPC
Q4 23/24 - Record standalone PAT and plant availability support a major hydro-led growth pipeline.NHPC
Q4 22/23 - Record availability and 380 MW added, offset by lower consolidated earnings and project risks.NHPC
Q4 17/18 - Higher FY17 profit and availability, offset by project delays and major shareholder payouts.NHPC
Q4 16/17