NHPC (NHPC) Q4 23/24 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 23/24 earnings summary
28 Oct, 2026Executive summary
FY2023-24 standalone PAT was ₹3,743.94 crore vs ₹3,833.79 crore; consolidated PAT was ₹4,028.01 crore, with ₹3,624.42 crore attributable to owners.
Generation was 21,779 MU and PAF 77.60%, down from 24,907 MU and 88.75%; flash floods and lower water inflows weighed on output.
Construction and development pipeline exceeded 10,000 MW, including 2,880 MW Dibang, 2,000 MW Subansiri Lower and expanding solar and pumped-storage projects.
Financial highlights
Standalone revenue from operations was ₹8,404.92 crore vs ₹9,316.34 crore; total income was ₹10,024.99 crore vs ₹10,150.90 crore.
Standalone total expenses rose 7.10% to ₹5,962.79 crore; other expenses increased ₹607.92 crore, partly offset by lower generation expenses, depreciation and finance costs.
Standalone PAT declined 2.34% to ₹3,743.94 crore; total comprehensive income fell 2.91% to ₹3,718.98 crore.
Consolidated total income was ₹10,993.91 crore vs ₹11,284.90 crore; PAT was ₹4,028.01 crore vs ₹4,260.83 crore.
Insurance claim income was ₹381.92 crore vs ₹19.33 crore; business-interruption loss recovery was ₹149.86 crore vs ₹42.14 crore, including ₹112.50 crore confirmed as an on-account payment.
Outlook and guidance
300 MW Bikaner and 100 MW N.P. Kunta solar projects were expected online in FY2024-25; 600 MW Kutch was targeted for FY2025-26, subject to transmission substation readiness.
Subansiri Lower targeted three units by March 2025 and all units by May 2026; Parbati-II anticipated commissioning was December 2024, while Dibang targeted February 2032.
The shareholder borrowing limit was proposed to rise from ₹40,000 crore to ₹50,000 crore; estimated debt needs for ongoing and new projects through FY2032-33 were ~₹80,000 crore.
Long-term outlook emphasizes hydropower, renewables, pumped storage and green hydrogen, supported by India’s 500 GW renewable-capacity target for 2030 and rising grid-balancing needs.
Latest events from NHPC
- H1 growth and hydro commissioning advanced amid higher costs and tariff uncertainty.NHPC
Q2 26/27 - Higher profit and availability, offset by project risks and audit qualifications.NHPC
Q4 01/02 - Higher earnings and collections, alongside ambitious hydro expansion and audit risks.NHPC
Q4 00/01 - Generation beat target, but state arrears and audit disputes clouded growth.NHPC
Q4 98/99 - Profit rose despite lower sales and generation shortfalls from weak river inflows.NHPC
Q4 99/00 - Record generation and earnings underpin a major hydro-renewables expansion.NHPC
Q4 21/22 - Record standalone PAT and plant availability support a major hydro-led growth pipeline.NHPC
Q4 22/23 - Record availability and 380 MW added, offset by lower consolidated earnings and project risks.NHPC
Q4 17/18 - Higher FY17 profit and availability, offset by project delays and major shareholder payouts.NHPC
Q4 16/17