NHPC (NHPC) Q4 98/99 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 98/99 earnings summary
28 Oct, 2026Executive summary
FY1998-99 net profit after prior-period adjustments was ₹3,053 million vs ₹2,994 million; gross sales including advance against depreciation rose to ₹13,094 million from ₹11,235 million.
Generation reached 9,917.51 MU, 16.40% above the 8,520 MU target; machine availability was 88.39%.
The year ended with ₹16,694 million in beneficiary-state receivables and a substantial construction pipeline, including Chamera Stage II, Teesta V and Parbati projects.
Financial highlights
Net sales after advance against depreciation were ₹11,944 million vs ₹9,930 million; other income was ₹391 million, including ₹344 million in the accounts.
Profit before depreciation, interest and financing charges was ₹9,545 million vs ₹7,809 million; profit after interest and depreciation, before prior-period adjustments, was ₹2,606 million vs ₹2,312 million.
Prior-period adjustments added ₹447 million vs ₹682 million, lifting reported profit for the year to ₹3,053 million vs ₹2,994 million.
Proposed dividend was ₹150 million; reserves and surplus increased to ₹12,721 million from ₹9,486 million.
Outlook and guidance
Rangit was expected to begin generation in December 1999; Dulhasti was scheduled for completion by March 2001, Dhauliganga Stage I by September 2004 and Kalpong by October 2002.
Chamera Stage II was approved on a turnkey basis at ₹16,840.2 million; Teesta V’s updated completion cost was ₹27,297.4 million, with clearances received and site infrastructure underway.
Teesta V was designed for 510 MW and 2,573 MU annual generation in a 90%-dependable year; Loktak Downstream was planned at 90 MW and 420.25 MU annually.
Teesta V, Loktak Downstream, Parbati and other projects were dependent on required clearances and project approvals; authorised share capital increase to ₹100,000 million was under government consideration.
Latest events from NHPC
- H1 growth and hydro commissioning advanced amid higher costs and tariff uncertainty.NHPC
Q2 26/27 - Higher profit and availability, offset by project risks and audit qualifications.NHPC
Q4 01/02 - Higher earnings and collections, alongside ambitious hydro expansion and audit risks.NHPC
Q4 00/01 - Profit rose despite lower sales and generation shortfalls from weak river inflows.NHPC
Q4 99/00 - Record generation and earnings underpin a major hydro-renewables expansion.NHPC
Q4 21/22 - Lower hydro output pressured earnings as a >10,000 MW clean-energy pipeline advanced.NHPC
Q4 23/24 - Record standalone PAT and plant availability support a major hydro-led growth pipeline.NHPC
Q4 22/23 - Record availability and 380 MW added, offset by lower consolidated earnings and project risks.NHPC
Q4 17/18 - Higher FY17 profit and availability, offset by project delays and major shareholder payouts.NHPC
Q4 16/17