Strategic direction and capacity

  • Vision 2032 targets 149 GW of capacity by 2032, supported by cumulative CapEx of INR 7 lakh crore through FY32; 82.6 GW is operational, 31 GW is under construction, and the portfolio totals 113.5 GW.

  • Coal capacity is targeted to rise by 26–27 GW, from ~62 GW to 88–89 GW within five years; 16.5–17 GW is awarded or in progress, with 7.2 GW of new thermal orders planned this FY.

  • Thermal strategy favors brownfield, mainly pithead, cost-plus projects using existing land and infrastructure; FY25 capacity additions were 4 GW, followed by 3 GW in FY26.

  • Renewable capacity is targeted to reach 60 GW by 2032 from 8 GW, with a pipeline exceeding 24 GW; ~6 GW of additions are planned this year, with 1.3–1.4 GW already added.

  • India's power demand is expected to rise with GDP growth, and per capita electricity consumption is projected to reach 3,000 kWh by 2050.

Transition and new businesses

  • Nuclear ambition is 30 GW by 2047; the Mahi Banswara JV is developing four 700 MW reactors, and 2.8 GW is targeted for award this fiscal.

  • Pumped-storage pipeline totals 21.37 GW; the FY32 target is 3–5 GW, with 1 GW planned for commissioning this fiscal and 500 MW at Tehri already in commercial operation.

  • Pudimadaka green hydrogen hub could require INR 80,000–85,000 crore of investment; a 1 TPD plant is under development at Simhadri, with green chemicals assigned to the renewable-energy business.

  • Storage and decarbonization work includes a 160 MWh CO2-based system at Kudgi, vanadium redox flow batteries, and CCUS; the CO2 system is planned for commissioning by July next.

  • Expansion into integrated energy includes bio-fuels and green mobility alongside renewables, hydrogen, chemicals, nuclear and storage.

Operational performance and sustainability

  • FY25 group generation reached a record 439 BUs, up 4%; coal-station PLF was 77.44%.

  • Forced outage rate was 3.42% in Q1 and 3.75% for FY25, versus 4.03% in the prior year; trade-receivable realization was 32 days, below the 45-day regulatory norm.

  • Captive coal production reached 46 million tonnes in FY25, up 28% YoY; the target is 50 million tonnes this year and at least 25% of coal needs from captive mining by FY30.

  • Coal capacity has 100% fuel tie-up, with 15% of coal sourced from captive mines; there has been no fuel supply under-recovery since FY20.

  • Sustainability measures include emission controls, water conservation, biomass co-firing and net-zero townships; over 40 million trees have been planted and a mega eco-park is under development.