NTPC (NTPC) Q1 26/27 earnings summary
Event summary combining transcript, slides, and related documents.
Q1 26/27 earnings summary
8 Oct, 2026Executive summary
Unaudited standalone and consolidated Q1 FY27 results were approved by the Audit Committee and Board on 24 July 2026; statutory auditors issued unmodified limited review reports.
Group installed capacity reached 90,904 MW at June 30, 2026, after 1,796 MW of Q1 additions; standalone capacity was 60,992 MW.
Standalone adjusted PAT rose to ₹5,128 crore from ₹4,413 crore YoY; consolidated net profit increased to ₹6,896.44 crore from ₹6,108.46 crore.
Financial highlights
Standalone revenue from operations was ₹43,831.86 crore, versus ₹42,571.61 crore in Q1 FY26; net profit was ₹5,342.36 crore versus ₹4,774.68 crore.
Standalone adjusted PAT was ₹5,128 crore, up from ₹4,413 crore YoY.
Consolidated revenue from operations was ₹50,740.96 crore, versus ₹47,064.35 crore; net profit was ₹6,896.44 crore versus ₹6,108.46 crore.
Consolidated profit included subsidiary profit of ₹1,204 crore and JV profit share of ₹628 crore.
Consolidated basic and diluted EPS, including regulatory deferral, was ₹6.93 versus ₹6.20 in Q1 FY26.
Outlook and guidance
Capacity under construction totaled 35,702 MW: 15,720 MW coal, 3,581 MW hydro and 16,401 MW renewable projects.
Pumped-storage portfolio stood at 18 GW; 5 GWh of BESS projects were awarded, with installations planned across 15 thermal stations and one group facility.
The 2,800 MW Mahi Banswara nuclear project advanced; excavation consent for Units I and II was received in March 2026.
Full Government of India compensation is expected for discontinued hydro project costs; outstanding recoverable was ₹374.99 crore.
Latest events from NTPC
- Capacity targets exceed 130 GW by 2032, led by renewables and regulated thermal growth.NTPC
Investor Day 2024 - FY32/FY37 capacity targets back a renewables-led expansion with INR 16.86 lakh crore planned.NTPC
Investor Day 2026 - PAT, capacity, and capex rose YoY; interim dividends declared; renewables and receivables improved.NTPC
Q3 25/26 - Capacity up 10% YoY, profit rises, and clean energy investments drive long-term growth.NTPC
Q2 2026 - INR 7 lakh crore backs a 149 GW vision spanning thermal and clean energy growth.NTPC
Investor Day 2025 - Standalone profit up 6% to ₹4,775 crore; capacity and renewables investments accelerate.NTPC
Q1 25/26 - Group PAT up 13% YoY, robust margins, interim dividend declared, and strong RE growth.NTPC
Q2 24/25 - FY25 net profit rose 12% to ₹23,953 crore, with record renewables and strong expansion targets.NTPC
Q4 24/25 - Q3 FY25 delivered robust growth with higher revenue, profit, and major renewable capacity expansion.NTPC
Q3 24/25