Santana Minerals (SMI) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
22 Sep, 2026Project overview and development status
Bendigo-Ophir Gold Project in New Zealand holds a reserve of 1.2 Moz at 2.6g/t gold, with mining and OIO permits secured and final approval expected by January 2027.
Project features a 14-year mine life, targeting up to 120,000 oz/year, with first gold production anticipated in 2028.
All-in sustaining cost is US$1,390/oz and total all-in cost is US$1,680/oz, supporting robust project economics.
Project NPV after tax is US$1.49 billion at a 6.5% discount rate, with an IRR of 85% and a payback period of 15 months from first gold.
Substantial exploration upside exists across 426 km², with four gold deposits and significant resource extension potential.
Financials and funding
Market capitalization is approximately A$550 million (US$390 million), with net cash of US$125 million.
Project financing requirement is estimated at A$277 million, with advanced debt funding underway.
Current enterprise value is A$375 million (US$265 million), and liquidity averages 3.1 million shares traded per day.
Project is included in the ASX 300 and GDXJ indices, with a strong cash position and set for a market re-rate.
Annual government tax and royalty contributions are projected at US$96 million.
Operations and infrastructure
Project benefits from low-cost hydro power, clean water, and proximity to major infrastructure, including a substation 8km away.
No FIFO or airstrips required; skilled residential workforce available locally.
Operational readiness includes management in place, mining fleet procurement, and early works such as new access roads and water infrastructure.
Development plan features multi-stage open pit and underground mining, with simple logistics and staged resource extraction.
Over 1,400 expressions of interest for employment have been received, supporting local job creation.
Latest events from Santana Minerals
- First gold is targeted for late 2028, with a 1.2 Moz reserve and A$2.1B NPV.SMI
Resources Rising Stars Gold Coast Conference - Final permit decision due December, enabling a high-margin gold project to break ground in Q1.SMI
Diggers & Dealers Mining Forum 2026 - Permitting, land acquisition, and exploration advances position the project for development.SMI
Q4 2026 TU - Raised A$134.1M, advanced permitting, and extended gold resources for robust project growth.SMI
Q3 2026 TU - Resource upgrade and robust economics drive project momentum, with strong cash reserves.SMI
H2 2024 - Bendigo-Ophir advances with robust PFS, resource growth, and strengthened financial position.SMI
H2 2025 - Development-ready gold project advances with strong cash, resource growth, and $130m raised.SMI
H1 2026 - Advancing a 2.34Moz NZ gold project with strong reserves, robust economics, and 2026 production target.SMI
Investor presentation - Bendigo-Ophir Gold Project advances toward construction with robust economics and resource growth.SMI