Logotype for Santana Minerals Limited

Santana Minerals (SMI) Q4 2026 TU earnings summary

Event summary combining transcript, slides, and related documents.

Logotype for Santana Minerals Limited

Q4 2026 TU earnings summary

28 Jul, 2026

Executive summary

  • Advanced the Bendigo-Ophir Gold Project (BOGP) through the Fast-track Approvals process, with a consent decision now expected by 16 December 2026.

  • Secured New Zealand OIO consent for the purchase of 3,680 hectares of freehold land, including buy-back of substantive royalties, improving project economics.

  • Completed the second tranche of a A$130 million equity placement, closing the quarter with A$188 million in net cash.

  • Advanced project readiness with new administration building, workforce accommodation, and ongoing exploration extending mineralisation at RAS and CIT.

Financial highlights

  • Closed the quarter with a cash balance of approximately A$188 million.

  • Spent A$5.5 million on project development and mining studies, A$3.2 million on environmental and FTA process, A$2.7 million on exploration, and A$3.3 million on plant and equipment.

  • Net cash from operating activities was negative A$185k for the quarter.

  • Net cash from investing activities was negative A$14.6 million for the quarter.

  • Net cash from financing activities was positive A$15.5 million for the quarter.

Outlook and guidance

  • Project remains on track for a Final Investment Decision following receipt of all necessary approvals.

  • Current project parameters based on June 2025 Updated Pre-Feasibility Study: 1.2Mtpa CIL plant, peak production ~120,000 oz/year, mine life ~14 years.

  • At prevailing gold prices (~A$5,750/oz), estimated after-tax NPV6.5 of A$1.9 billion and IRR of 78%.

  • Exploration results indicate potential for significant resource growth and mine life extension.