9 Sep, 2026Project development and approvals
Rapid progress from discovery to development, with first gold targeted for late 2028 and final approval expected by January 2027.
Mining permit granted in November 2025 and OIO consent in May 2026, with advanced permitting milestones including expert hearings and management plan certification.
Fast-track Approvals Act streamlines permitting, with 26 mining and other projects already approved.
Project is well-funded, with a bank balance near AUD 180 million and a market cap of AUD 520 million.
Operational readiness includes management in place, mining fleet procurement, and infrastructure development such as new access roads and power lines.
Resource and exploration highlights
Bendigo-Ophir project hosts 2.34 million ounces, with the Rise and Shine deposit containing over 2 million ounces.
Maiden reserve of 1.2 million ounces at 2.6g/t gold announced in late 2024, updated with a PFS in mid-2025.
93% of production target is within indicated resources, with ongoing exploration upside across 426 km² and 30km of strike.
Recent drilling extends high-grade zones, with intercepts such as 11 m at 8.5 g/t and 37 m at 1.7 g/t, and significant down-plunge extension at the Rise & Shine deposit.
Soil anomalies and new targets identified through mapping and sampling, supporting further resource growth.
Mine plan and operational readiness
Staged open pit transitioning to underground mining, with underground development starting in year five and approximately 1 Moz from open pit.
Targeting 120,000 oz annual production by year two, with a 1.2 Mtpa mill.
Pre-strip of 17 million tons to expose ore, allowing time for plant construction and commissioning.
Komatsu mining fleet commissioned, exploration base and infrastructure in place.
Skilled residential workforce available, with strong local interest and support.
Latest events from Santana Minerals
- Final permit decision due December, enabling a high-margin gold project to break ground in Q1.SMI
Diggers & Dealers Mining Forum 2026 - Permitting, land acquisition, and exploration advances position the project for development.SMI
Q4 2026 TU - Raised A$134.1M, advanced permitting, and extended gold resources for robust project growth.SMI
Q3 2026 TU - Resource upgrade and robust economics drive project momentum, with strong cash reserves.SMI
H2 2024 - Bendigo-Ophir advances with robust PFS, resource growth, and strengthened financial position.SMI
H2 2025 - Development-ready gold project advances with strong cash, resource growth, and $130m raised.SMI
H1 2026 - Advancing a 2.34Moz NZ gold project with strong reserves, robust economics, and 2026 production target.SMI
Investor presentation - Bendigo-Ophir Gold Project advances toward construction with robust economics and resource growth.SMI
Q2 2026 TU - Strong financials and rapid project development hinge on permitting and funding outcomes.SMI
AGM 2024