Savannah Resources (SAV) H1 2024 earnings summary
Event summary combining transcript, slides, and related documents.
H1 2024 earnings summary
2 Apr, 2026Executive summary
Secured a strategic partnership with AMG Critical Materials, providing £16m in equity and a pathway to full project financing for the Barroso Lithium Project.
Advanced the Definitive Feasibility Study (DFS) and environmental licensing, with DFS completion now expected in H2 2025 and project commissioning in 2027.
Strengthened the management team and board, including the appointment of a new Chairman and AMG's board representative.
Enhanced stakeholder engagement and increased in-country shareholding to over 12.5%.
Financial highlights
Cash position reached a record £21.6m at 30 June 2024, up from £4.8m at 30 June 2023, following the AMG investment.
Loss from continuing operations increased 27% year-over-year to £1.9m (H1 2023: £1.5m), reflecting higher activity and workforce expansion.
Intangible assets rose by £1.5m to £19.9m, and property, plant, and equipment increased to £1.7m due to ongoing land purchases.
Total equity grew 50% from year-end 2023 to £41.8m.
Outlook and guidance
DFS and environmental licensing expected to complete in H2 2025, with project commissioning and first production targeted for 2027.
Project timeline aligns with forecasts for tighter lithium markets and higher prices from 2027 onward.
Focus remains on progressing to Final Investment Decision, leveraging strong cash reserves and strategic partnerships.