Savannah Resources (SAV) H1 2025 earnings summary
Event summary combining transcript, slides, and related documents.
H1 2025 earnings summary
2 Apr, 2026Executive summary
Barroso Lithium Project classified as a 'Strategic Project' by the European Commission under the Critical Raw Materials Act, securing political and regulatory support.
Significant progress on the Definitive Feasibility Study (DFS), with resource-focused drilling completed and a new JORC Resource estimate published post-period.
Upgraded and expanded JORC Resource to 39.1Mt at 1.05% Li₂O, a 40% increase in tonnage and 41% increase in contained Li₂O year-over-year.
Strong stakeholder engagement, including local community initiatives and increased Portuguese shareholder base.
Cash position strengthened post-period by a £4.78m fundraise, supporting ongoing project development.
Financial highlights
Cash position at 30 June 2025 was £9.5m, rising to £13.3m in July after the fundraise.
Losses from continued operations decreased by 21% year-over-year to £1.5m (H1 2024: £1.9m), mainly due to lower administrative expenses and a £0.2m FX gain.
Exploration expenditure increased by 39% to £3.2m (H1 2024: £2.3m) due to intensified project activity.
Intangible assets grew by 19% to £25.8m, with total assets at £42.2m.
No revenue generated; operations remain pre-production.
Outlook and guidance
DFS and environmental licensing expected to complete in H1 2026, with first production targeted for 2028.
Ongoing engagement with potential commercial partners, finance providers, and public funding sources.
Market conditions for lithium have improved, with spodumene concentrate prices up over 30% since mid-June 2025.
Additional funding will be required in H1 2026 to finalize DFS and move to construction.